Try our mobile app

McEwen Mining: Fenix Project Feasibility Study

Published: 2020-12-31 11:55:00 ET
<<<  go to MUX company page

A Near Term Production Opportunity

TORONTO, Dec. 31, 2020 (GLOBE NEWSWIRE) -- McEwen Mining Inc. (NYSE: MUX) (TSX: MUX) is pleased to announce the highlights of a positive Feasibility Study (FS) for its 100%-owned Fenix Project, which is located in the State of Sinaloa, Mexico.

“The Fenix Feasibilty Study envisions a 9.5-year mine life with an attractive after-tax IRR of 28% using $1,500/oz gold and $17/oz silver. At current gold and silver prices, the project’s after-tax IRR almost doubles and the NPV more than triples versus the base case.

The project will incorporate an environmentally progressive method of tailings management, using inpit storage that creates multiple benefits, most importantly a secure containment of tailings enabling better reclamation results.

Average annual production is projected at 26,000(1)oz gold in Phase 1 and 4,200,000(4)oz silver equivalent in Phase 2. The critical path environmental permits are in hand for the first phase of production. Our next steps will involve detailed engineering, assessment of procurement options, and the evaluation of financing alternatives,” said Rob McEwen, Chairman and Chief Owner.

Fenix FS Highlights

  Base Case(1)$1,500/oz Gold, $17/oz SilverUpside Case$1,900/oz Gold, $25/oz Silver
After-Tax IRR28%55%
After-Tax NPV (8% discount)$32 million$98 million
After-Tax Payback Period3.6 years2.8 years
Average After-Tax Cash Flow per Year of Full Production$12 million$25 million
 The FS for project Fenix development involves two phases:
  
 Phase 1: Years 1 to 6, Gold Production
 
  • Average Annual Gold Production 26,000 oz Au
  • $42 million initial capex
  • $1,035 cash cost(2) and$1,042 AISC(3) per oz Au
  
 Phase 2: Years 7 to 9.5, Silver Production  
 
  • Average Annual Silver Production 4,200,000 oz AgEq.(4)
  • $24 million incremental capex in Year 6.
  • $14.20 cash cost(2) and$14.28 AISC(3) per oz AgEq.(4)

Feasibility Study Report

The complete Fenix Project FS NI 43-101 Technical Report will be available on www.sedar.com and www.mcewenmining.com within 45 days. The FS was prepared by GR Engineering Services Limited (“GRES”) of Belmont, Western Australia, in accordance with the requirements of Canadian National Instrument 43-101 “Standards of Disclosure for Mineral Projects” (“NI 43-101”) and SEC Industry Guide 7.

Permits

The current operation at El Gallo Gold is a fully permitted site; permit for the Phase 1 was granted by the Federal Environmental Authority (SEMARNAT) in September 2019, for the addition of a mill and leach circuit in the location of the existing facilities for the reprocessing of the heap leach pad material. The permit amendment also includes the backfilling of a previously mined pit with mill tailings, as part of an integrated concurrent closure plan for the El Gallo Gold Mine.

Further project advancement for Phase 2 is subject to permit approvals. Phase 2 project permitting will require authorization to expand the process plant footprint at El Gallo Gold and the haul road, and to augment the tailings volume to be deposited at the depleted pit.

The Fenix Project has CONAGUA approval for the extraction of groundwater and land-use permits for the construction of wells required for the life of Fenix Project.

Resource Estimates

Estimated resources for the Fenix Project are comprised only of material within the boundaries of conceptual pit shells, except for the El Gallo heap leach pad, which is considered completely available for reprocessing.

For the purposes of mine scheduling, the contained gold ounces in the Heap Leach Material has been depleted from the resource model estimate defined by drilling by an amount of 23 koz Au, to account for the production from heap leach operations and gold in circuit assessments between the timing of the resource estimate up until December 2020.

Table 1: Fenix Project Resources Estimate(5)(6)

Heap Leach Material(7)Tonnes Silver Grade Silver Gold Grade Gold 
Potential COG = 0 g/t AuMt (g/t) koz (g/t) koz 
Measured8.8 1.59 451 0.59 167 
Indicated1.2 1.74 67 0.60 23 
Measured and Indicated10.0 1.61 518 0.59 190 
Inferred0.1 1.64 7 0.66 3 
El Gallo Silver          
In Optimized Pit ShellTonnes Silver Grade Silver Gold Grade Gold 
Potential COG = 58 g/t AgMt (g/t) koz (g/t) koz 
Measured1.0 155.38 4,791 0.08 3 
Indicated3.5 126.55 14,228 0.13 15 
Measured and Indicated4.5 132.76 19,019 0.12 18 
Inferred0.1 128.92 286 0.14 0.3 
COMBINED RESOURCES          
In Optimized Pit ShellsTonnes Silver Grade Silver Gold Grade Gold 
Potential COGs variable Mt (g/t) koz (g/t) koz 
Measured9.8 16.68 5,242 0.54 170 
Indicated4.7 94.58 14,295 0.25 38 
Measured and Indicated14.5 41.98 19,536 0.45 208 
Inferred0.2 46.50 293 0.48 3 

Table 2: Fenix Project Reserves Estimate(8)

Heap Leach MaterialTonnes Silver Grade Silver Gold Grade Gold 
Mt (g/t) koz (g/t) koz 
Proven8.8 1.59 451 0.59 167 
Probable1.3 1.57 67 0.54 23 
Proven + Probable10.1 1.58 517 0.58 190 
El Gallo Silver          
Proven0.7 165.71 3,708 0.05 1 
Probable3.7 126.61 15,017 0.13 16 
Proven + Probable4.4 132.82 18,725 0.12 17 
COMBINED RESERVES          
Proven9.5 13.60 4,159 0.55 168 
Probable5.0 93.46 15,084 0.24 39 
Proven + Probable14.5 41.19 19,243 0.44 207 

Table 3: Assumptions for Heap Leach Pad and El Gallo Silver Pit Optimization Phase 2(6)(9)

Assumptions for In-Pit Resource Shells DepositsValues
Gold PriceAll$1,300/oz
Silver PriceAll$16.00/oz
Mining CostHeap Leach Pad$0.53/t
 El Gallo Silver$12.06/t
Processing and G&AHeap Leach Pad$12.88/t
 El Gallo Silver – Oxides$26.90/t
 El Gallo Silver– Sulfides$25.93/t
Recovery - AuHeap Leach Pad85.90%
 El Gallo Silver79.40%
Recovery - AgHeap Leach Pad45.0%
 El Gallo Silver – Oxides82.5%
 El Gallo Silver– Sulfides88.1%
Cut-Off GradeHeap Leach Pad0 g/t Au
 El Gallo Silver58 g/t Ag
Inter-Ramp Pit Slope AngleEl Gallo Silver45 degrees

FOOTNOTES (1) The Base Case utilizes the three-year moving average prices for gold and silver (approximate value). Estimated 26,000 oz Au per annum production assumes full production from years 2023 to 2027. Average after-tax cash flow per annum from full production years 2023 to 2031 is approximately $12 million per annum. Average after-tax cash flows per annum for the period from start-up of production to closure (2022 to 2032) is approximately $8.6 million per annum. These cash flows assume the use of all eligible tax loss carry forwards from the El Gallo Gold Mine.(2) Cash cost is calculated by dividing total life-of-mine production costs, general and administrative expenses and royalties by total ounces produced.(3) All-in sustaining costs (AISC) are calculated by dividing the sum of all cash costs plus sustaining capital and reclamation costs by total ounces produced.(4) All references to AgEq are based on an 88 Ag oz to 1 Au oz ratio. For Phase 1 silver accounts for