Try our mobile app

South Africa’s next big energy challenge: a R390-billion grid upgrade

Published: 2024-03-15 14:30 +02:00 by Paul Burkhardt tag: Energy

JSE:MPT JSE:ISA

The country needs to build and fund a R390-billion expansion of the national grid so it can connect more power plants.
South Africa is facing a monumental challenge as it seeks to end years of rolling electricity outages that have hobbled the economy: it needs to build and fund a R390-billion expansion of the national grid so it can connect more power plants.

The transmission system is owned, managed and maintained by Eskom, which supplies more than 80% of the country’s electricity and has failed to properly maintain its plants or expedite the process of building enough new ones to avert energy shortages.

The state utility plans to build 14 218km of power lines over the next decade, more than three times what it has installed over the past 10 years. It will also have to increase its transformer capacity six-fold and build other infrastructure.

Load shedding has curbed output, stoked unemployment and limited economic growth

Load shedding has curbed output, stoked unemployment and limited the annual economic growth rate to an average of less than 1% over the past decade — key campaign issues heading into the 29 May election. In its election manifesto, the ANC said it would “prioritise investment in expanding the transmission grid so that more energy, including from renewable sources, can be supplied”, a pledge echoed by its main rivals.

Funding the expansion appears beyond Eskom’s reach. The company’s coffers were systematically looted during former President Jacob Zuma’s almost nine years in office and it amassed more than R400-billion in debt before national treasury stepped in with a conditional bailout that severely constrains the loss-making utility from taking on additional loans.

The failure to invest adequately in the grid has created “a real emergency”, said Brian Day, chairman of the South African Independent Power Producers Association. The construction of new lines and substations is proceeding too slowly and needs to be ramped up, he said.

Grid constraints

Inadequate transmission infrastructure is already frustrating efforts to increase the electricity supply. After calling for bids that would double wind-power purchases from private contractors, the government failed to award any of the contracts because the projects couldn’t be connected.

Grid constraints also pose a risk to an estimated 66GW of wind and solar plants that are already at various stages of development in South Africa, Raine Adams, an analyst at fund manager Allan Gray, wrote in a note to clients.

South Africa began developing its electricity system more than a century ago, building power stations adjacent to rich coal deposits in the north-east of the country to provide the energy needed to extract gold and other minerals. Transmission lines were later added to connect up other parts of the country.

Read: South Africa a step closer to liberalising electricity sector

Over recent years, several solar and wind plants constructed by private developers have been connected to the grid but link-ups in the areas best suited for such facilities have run out — an issue that needs to be resolved if the country is to meet its commitments to lower its greenhouse gas emissions.

Eskom listed “statutory approvals and procurement turnaround times, followed by capital budgets”, as the biggest obstacles it faces in expanding the grid. Securing the land rights to lay cables and tackling the organised crime that pervades South Africa’s construction industry are also potential challenges, it said.

Even if it could raise the money, the utility’s ability to roll out the required additional lines would remain in question, given its tarnished track record implementing other megaprojects, including the construction of two of the world’s biggest coal-fired plants. Announced in 2007, Medupi and Kusile were scheduled to be completed within eight years at a total cost of R163-billion, but the likely final price tag has since ballooned to more than R460-billion and both still aren’t running at full capacity.

“The grid delivery will be a challenge, but steps are being taken to learn from the experiences from the Medupi and Kusile projects, and to avoid repeating the mistakes,” Eskom said, adding it will consider outsourcing part of the work. The utility will return to the capital markets beyond its 2026 financial year, and expects to finance transmission infrastructure using a blend of equity and debt.

“At present, Eskom is not financially sustainable on a standalone basis and financial institutions are unlikely to provide additional funding in the absence of a government guarantee or other form of credit enhancements,” said Lindani Vezi, a listed credit investment analyst at Cape Town-based Futuregrowth Asset Management.

Financial institutions are unlikely to provide additional funding in the absence of a government guarantee

Cabinet has endorsed the creation of an Independent Transmission Projects Office to help garner private financing for the grid, a model that’s been used in countries such as Brazil and India, according to electricity minister Kgosientsho Ramokgopa.

While he sees an “insatiable appetite” among private companies to invest in transmission, multiple procedural delays — including a protracted breakup of Eskom into generation, transmission and distribution units that would help facilitate access to the grid — have stalled the process.

The ANC is adamant the transmission network won’t be privatised.

“Transmission projects are often strategic assets and so financing by private investors can be seen as a loss of control to the sponsoring country,” said Sanjeet Sanghera, head of grids and utilities at BloombergNEF. “There is a need for a model that strikes the right balance.”

‘Sliver of hope

Hilton Trollip, an energy research consultant at the University of Cape Town, said that despite anticipated delays and resistance to private sector participation in the grid, some progress has been made in easing regulations and improving the utilisation of the existing grid.

The government’s “recent flexibility gives a sliver of hope”, he said. — Reported with assistance from Gem Atkinson, James Herron and Paul Richardson, (c) 2024 Bloomberg LP

Get breaking news alerts from TechCentral on WhatsApp