FINANCE DIRECTOR’S PRE-CLOSE MESSAGE
Six-month period ending 30 June 2023 (1H23) (the period)

This is an overview of the group’s expected business performance for 1H23, encompassing strategic,
operational, and financial information. Unless otherwise indicated, all comparisons are against the six-
month period ended 31 December 2022 (2H22).

DEAR STAKEHOLDER
As of 15 June 2023, Exxaro recorded six lost time injuries resulting in a lost time injury frequency rate
(LTIFR) of 0.10 against the set target of 0.05. The current LTIFR indicates a 40% decline in performance
when compared to the same period last year. However, year-to-date, Exxaro has recorded two High
Potential Incidents across the group, compared to five for the full year ended 31 December 2022. To prevent
and mitigate further incidents, various safety initiatives have been deployed across all our business units.
Following China ending its zero-COVID policy, and despite the continued challenges of high inflation,
tightening financial conditions and geopolitical conflicts, the global economy has so far managed to avert a
recession. This negative global sentiment was, however, evident throughout the period under review and
weighed on commodity markets.
In respect of Exxaro’s key commodities, the average benchmark API4 Richards Bay Coal Terminal (RBCT)
export price for 1H23 is expected to average US$127 (2H22: US$265) per tonne, a significant decline from
the previous six months, and the iron ore fines price for 1H23 is expected to average US$117 (2H22:
US$101) per dry metric tonne, cost, and freight (CFR) China.

Total coal production (excluding buy-ins) and sales volume for 1H23 are expected to decrease by 4% and
7% respectively, due to reduced demand from Eskom as well as logistical constraints. A new Coal Supply
Agreement (CSA) is currently under negotiation with Eskom in relation to the Matla mine. In the interim, the
current CSA is being extended by a year.
In terms of our capital allocation programme, we expect the capital expenditure for 1H23 in our coal
business to be about 8% lower, due to key projects reaching completion in 2022 as well as optimising
benefits from our capital excellence program.
As at 31 May 2023, the group had net cash of R12.0 billion (excluding Cennergi’s net debt of R4.3 billion).
The group therefore has sufficient liquidity and will remain a going concern for the foreseeable future.
We will provide a detailed account of 1H23 business performance and an outlook on the subsequent six
months (2H23) when we announce our interim results on or about 17 August 2023.

Yours sincerely
Riaan Koppeschaar
Finance Director




                                                                                                          1
MACRO-ECONOMIC ENVIRONMENT
GLOBAL ECONOMY AND COMMODITY PRICES
World real GDP growth increased from an annual rate of 1.6% quarter on quarter in 4Q22 to 2.5% in 1Q23.
A mild deceleration is expected in the second quarter; however, moderate growth is anticipated to be
sustained for the rest of 2023. After a 3.1% increase in 2022, world real GDP is expected to expand by a
moderate 2.3% in 2023.
During 1H23, seaborne thermal coal prices have remained under pressure due to weak demand in Europe
and Northeast Asia. Both thermal coal and gas prices declined significantly to levels last recorded two years
ago. Europe remains very well stocked for both gas and thermal coal. Stronger renewables availability also
boosted base load generation, further reducing the role of gas and thermal coal in the European energy
mix.
Since the beginning of 2023, seaborne iron ore prices have been supported by positive market sentiment
for demand recovery for steel in China. This was before the announcement of China’s government
considering to potentially limit or even reduce crude steel output during 2023, which resulted in declining
seaborne prices. China’s steel production quotas were confirmed in May, at local, and not at national level,
limiting the adverse impact on iron ore prices. Iron ore supply was strengthening towards the end of the
period under review, although demand remained weak. However, positive market sentiment returned in
response to the expectation that the Chinese government would further relax policy restrictions in the real
estate market.

OPERATIONAL PERFORMANCE
COAL OPERATIONS

MARKETS
The bearish market sentiment in 1H23 is characterised by price declines, due to sufficient gas and coal
stocks in Europe, exacerbated by warmer than usual winter temperatures, strong renewables performance,
and materially lower gas prices.
The lower coal prices resulted in an increase in demand for South African coal from India. Demand from
India retreated in 2022 due to the soaring prices.
Changes in global trade flows are seen, as Australia resumed supply into China, and Russian supplies to
Europe and Japan reduced materially.
Europe’s reassessment of coal-fired power capacity for the upcoming winter is continuing, with mixed
decisions from different governments, as the drive to phase out coal gains momentum in that region.
The decline in export prices has impacted exporters’ ability to truck coal economically to alternative ports.
Domestic end-use demand for coal remained stable, but an increase in coal inventory levels across the
industry value chain is evident due to export logistical constraints.




                                                                                                           2
PRODUCTION AND SALES VOLUMES
TABLE 1: Coal product and sales volumes
                                        Product                                                        Sales
 ‘000 tonnes            1H23        2H22    %                            FY22          1H23        2H22    %           FY22
                        Forecast1 Actual Change                          Actual        Forecast1   Actual Change       Actual
 Thermal production /
                        19 078      20 496 (7)                           41 136        16 593      18 007   (8)        36 188
 sales
   - Eskom                                                                             11 780      12 577   (6)        25 392
   - Domestic                                                                          2 116       2 357    (10)       4 639
   - Tied2                                                                             2 697       3 073    (12)       6 157
 Buy-ins                175         4       >100                         20
 Total thermal product
                        19 253      20 500      (6)                      41 156
    (Including buy-ins)
    Total Metallurgical
                                 1 417          904         57           1 988         358         288      24         691
    production / sales
    Exports                                                                            2 511       2 672    (6)        5 214
    Total product                20 670         21 404      (3)          43 144        19 462      20 967   (7)        42 093
1
Based on the latest internal management forecast assumptions. Final numbers may differ by ±5%.
2
Matla Mine supplying its entire production to Eskom.


Production
Thermal Coal production is expected to decrease by 7%, mainly due to lower demand from Eskom at
Grootegeluk, based on their latest internal planning requirements.
Metallurgical coal production is expected to increase by 57% as the GG6 plant now fully ramped up.
Coal buy-ins are expected to be higher, driven by logistical challenges and timing of sales obligations.


Sales
Sales to Eskom are expected to decrease by 6% in line with their demand.
Domestic thermal coal sales are expected to decrease by 10% due to the slower diversion of export coal
into the local market, mainly at the Mpumalanga mines.
Metallurgical coal sales are expected to increase by 24%, as alternative transport arrangements are
enabling supply to our local customers.
Export sales volumes are expected to decrease by 6% due to poor rail performance to RBCT as well as
the viability of trucking coal to alternative ports being negatively impacted by the lower coal prices.

Tied mine (Matla)
Thermal coal production and sales volumes are both expected to decrease by 12% due to unfavourable
geological conditions.

LOGISTICS AND INFRASTRUCTURE
Transnet Freight Rail (TFR) railed 19.948Mt to RBCT for the five months ended 31 May 2023, equivalent
to an annualised rate of 46.46Mtpa. Various challenges, including poor locomotive availability, train
derailments, and instances of cable theft and vandalism continue to impact negatively on export
performance.
TFR and the coal industry continue to collaborate on efforts to improve rail performance. Industry has
supported various initiatives during the past six months and continues to engage to support improvement
initiatives.

ENERGY OPERATIONS

                                                                                                                   3
Cennergi’s operating wind assets are forecasting to generate 318 GWh of electricity by 30 June 2023
(2H22: 364 GWh and FY22: 671 GWh). Tsitsikamma experienced an Eskom distribution line fault resulting
in 15GWh of lost generation over a one-month period of the fault. An improvement in wind conditions is
observed from the prior year. The average plant availability is forecast to be above the contracted
availability of 97%.

Financial close of the 68 MW Lephalale Solar PV Project (LSP) at Grootegeluk is imminent.

CAPITAL ALLOCATION
Exxaro remains focused on optimising and implementing its portfolio of sustaining capital.
TABLE 2: Coal Capex
                             1H23           2H22          %            FY23           FY23             %            FY22
    R’million                Forecast1      Actual        Change       Forecast1      Previous         Change       Actual
                                                                                      Guidance2
    Sustaining               736            678                9       2 211          2 500            (12)         1 374
    Expansion                73             202              (64)      73             0                100          231
    Total                    809            880               (8)      2 284          2 500            (9)          1 605
1
Based on latest internal management forecast assumptions and estimates (excluding Matla). Final numbers may differ by ±5%.
2
Provided on the 31 December 2022 results presentation held on 16 March 2023.

Capital expenditure is expected to be 8% lower in 1H23, with sustaining capital expenditure expected to
decrease at Grootegeluk, offset by higher spend at Leeuwpan and Belfast in the latter half of 2023. The
decrease of 64% in expansion capital is due to the conclusion of the GG6 project in 2022, as guided
previously.
FY23 capex is expected to be in line with our earlier guidance of R2.5 billion (on average in real terms).
Capex is regularly reviewed and projects re-prioritised as part of the Capital Excellence journey to optimise
planning, timing, cost, and business impact.
GG6 EXPANSION
The GG6 expansion project is complete, with final administrative project close out expected in 2H23.
MATLA MINE 1
The Matla Mine 1 Relocation project commenced with construction in August 2020. We received
intermediate approval on the Northwest Access in 1H22. In 1H23 Eskom approved Mine 1 Relocation
funding of R1.4 billion. Expected completion date of the project is 1H26.
MORANBAH SOUTH
The pre-feasibility study to determine the way forward for the Moranbah South hard coking coal project is
being re-scoped, with the intent of commencing with the revised scope in 2H23.

PORTFOLIO OPTIMISATION

INVESTMENT IN GROWTH
We actively evaluate and participate in investment processes for our minerals and energy businesses.

SALE OF NON-CORE ASSETS AND INVESTMENTS
As part of the broader Exxaro strategic review, the company continuously seeks opportunities to unlock
value to support its Sustainable Growth and Impact strategy. Exxaro has identified that the FerroAlloys
business is no longer considered a strategic fit within our envisaged Minerals business portfolio. We,
however, believe that there is still significant value to be unlocked in the hands of a potential buyer and
have therefore decided to commence a sales process to dispose of our entire shareholding in Exxaro
FerroAlloys Proprietary Limited.
Exxaro is perusing its options to dispose of its 26% shareholding in Black Mountain.

SUSTAINABLE DEVELOPMENT

                                                                                                                             4
CLIMATE CHANGE RESPONSE STRATEGY IMPLEMENTATION
Our decarbonisation roadmap to carbon neutrality by 2050 currently reflects our revised short-term
emission reduction target of 40% (vs 43%) by 2026, which is based on the FY22 emissions. The 40%
emissions reduction target will be achieved through energy efficiency projects, which have been
implemented thus far at our operations and contribute to a 2% reduction in Scope 1 emissions, the LSP
project at Grootegeluk which will reduce the group’s Scope 2 emissions by 27%, and further portfolio
optimisation initiatives, which will result in a further 9% reduction in emissions.

SOCIAL INVESTMENT AND DEVELOPMENT
For the six-month period ending 30 June 2023, Exxaro invested approximately R625 million through both
coal and energy operations, including over R500 million on local procurement, on various community
development initiatives despite a challenging business environment. Combined, these initiatives supported
228 SMME’s and provided 360 employment opportunities.

MINING AUTHORISATIONS AND RIGHTS
We submitted the Environmental Impact Assessment report for the Belfast Expansion Project to the
Department of Mineral Resources and Energy (DMRE) with approval expected in 4Q23. The Belfast mine
has a valid water use license, which is currently being amended.
Matla’s renewal application of the waste management license for the brine pond was recently submitted to
the Department of Forestry, Fisheries and the Environment in June 2023 with approval expected in 4Q23.
Matla’s water use licence renewal is currently in process and approval is expected in 4Q23.
Leeuwpan’s amendment application for its water use license is in preparation and submission to the
Department of Water and Sanitation is expected at the end of June 2023, with approval in 1Q24.
The DMRE still faces challenges with a backlog of applications. Exxaro has the following applications in
process at the DMRE:
• The execution of Grootegeluk’s section 102 application amending the mining right boundary.
• The execution of Leeuwpan’s section 102 application combining the two mining rights into a single
    mining right.
• A section 102 application amending Matla’s mining right to swap Coal Reserves with Seriti Resources
    as part of a commercial transaction.

OUTLOOK FOR 2H23

ECONOMIC CONTEXT
Although global inflation is on a downward path, underlying inflationary pressures persist. Policy interest
rates are at or near their peaks, although a further tightening of bank lending standards will contribute to
more restrictive financial conditions, affecting both global investment sentiment and economic activity.
Following a 1.1% contraction of GDP in the fourth quarter of 2022, South Africa avoided a technical
recession during the first quarter of 2023, with a modest 0.4% expansion.
During 1H23, the Rand lost significant value against the major global currencies. Intensified load shedding
with the perceived risk of a potential grid collapse, a widening current-account deficit, prospects of a
widening fiscal deficit, US dollar strength and loss in investor interest following a political dispute between
South Africa and the US, related to South Africa’s relations with Russia, were the main reasons attributed
to the rand weakness.
Rand volatility is expected to remain elevated during the second half of 2023.

COMMODITY MARKETS AND PRICE

Rising industrial activity and hot northern hemisphere summer weather have the potential to support energy
demand during 2H23. Furthermore, despite Europe’s comfortable energy status currently, risks for the
winter energy supply remain. Europe’s winter energy security depends on a range of uncertain and



                                                                                                             5
uncontrollable factors, including weather, the availability of liquefied natural gas and the risk of further gas
cuts from Russia.

Rising iron ore supply and exports will be a limiting factor for iron ore prices during 2H23. Supply increases
from major miners are expected, with a flat Chinese demand. Seaborne price volatility around the marginal
cost level is likely to see marginal supply exit, rebalancing the market and providing limited price support.

BUSINESS PERFORMANCE
Our coal business performance continues to be impacted by logistical challenges, persistent inflation, and
low coal prices. Our Optimisation programmes focus on reducing cost and improving efficiencies across
the value chain, thus protecting our business from these external factors. The Digital programme and
advanced analytics provide visibility and insights, which enable our business to be responsive and resilient,
throughout the prevailing economic conditions.

REVIEW OF THE UPDATE
The information in this update is the responsibility of the directors of Exxaro and has not been reviewed or
reported on by Exxaro’s independent external auditors.

TELECONFERENCE CALL DETAILS
A dial-in teleconference call on the details of this announcement will be held on Tuesday,
27 June 2023 starting at 12:00 SAST.

PRE-REGISTRATION LINK
Participants must pre-register for the conference through the link below:
https://services.choruscall.za.com/DiamondPassRegistration/register?confirmationNumber=9862547&linkSecurityString=190f3f1773

Please note that only registered participants will receive a dial-in number upon registration.

CONFERENCE REPLAY
A conference replay will be available one hour after the end of the conference until 30 June 2023. To access
the playback, dial one of the following numbers using the playback code 44574#:
•        South Africa                                      010 500 4108
•        UK                                                0 203 608 8021
•        Australia                                         073 911 1378
•        USA                                               1 412 317 0088
•        International                                     +27 10 500 4108
To access the replay using an international dial-in number, please select the link below.
https://services.choruscall.com/ccforms/replay.html

LEAD EQUITY SPONSOR AND DEBT SPONSOR
Absa Bank Limited (acting through its Corporate and Investment Banking division).




JOINT EQUITY SPONSOR
Tamela Holdings Proprietary Limited




EDITOR’S NOTE

                                                                                                                          6
Exxaro is one of the largest South Africa-based diversified resources companies, with main interests in
coal, iron ore and renewable energy commodities. www.exxaro.com
Interim results for the six-month period ending 30 June 2023 will be announced on or about
17 August 2023.

ENQUIRIES
Mzila Mthenjane, Executive Head: Stakeholder Affairs
Tel: + 27 12 307 7393
Mobile: +27 83 417 6375
Email: Mzila.mthenjane@exxaro.com

LEGEND
4Q22 – Fourth quarter ended 31 December 2022
1H22 – Six-month period ended 30 June 2022
2H22 – Six-month period ended 31 December 2022
FY22 – Financial year ended 31 December 2022
1Q23 – First quarter ended 31 March 2023
1H23 – Six-month period ending 30 June 2023
4Q23 – Fourth quarter ending 31 December 2023
2H23 – Six-month period ending 31 December 2023
FY23 – Financial year ending 31 December 2023
1Q24 – First quarter ending 31 March 2024

COMMODITY PRICES SOURCE
Coal – IHS Energy
Iron ore – MB Online

DISCLAIMER
The operational and financial information on which any outlook or forecast statements are based has not
been reviewed nor reported on by the group’s external auditor. These forward-looking statements are based
on management’s current beliefs and expectations and are subject to uncertainty and changes in
circumstances. The forward-looking statements involve risks that may affect the group’s operational and
financial information. Exxaro undertakes no obligation to update or reverse any forward-looking statements,
whether because of new information or future developments.