Eastern Platinum Limited Reports Q3 2021 Results

Published: 2021-11-11 06:45:00 ET
<<<  go to JSE:EPS company page
Eastern Platinum Limited (JSE:EPS) News - Eastern Platinum Limited Reports Q3 2021 Results

EASTERN PLATINUM LIMITED
(Incorporated in Canada)
(Canadian Registration number BC0722783)
(South African Registration number 2007/006318/10)
Share Code TSX: ELR ISIN: CA2768555096
Share Code JSE: EPS ISIN: CA2768555096
(“Eastplats” or the “Company”)

November 11, 2021


                                                 NEWS RELEASE

     EASTERN PLATINUM LIMITED REPORTS RESULTS FOR THE THIRD QUARTER OF 2021

November 11, 2021, Vancouver, British Columbia – Eastern Platinum Limited (“Eastplats” or the “Company”) is
pleased to report that it has filed its condensed interim consolidated financial statements and management’s discussion
and analysis for the three and nine months ended September 30, 2021. Below is a summary of the Company’s financial
results for the third quarter of 2021 (“Q3 2021”) and for the nine months ended September 30, 2021 (“YTD Q3 2021”)
(all amounts in USD unless specified) in comparison to the same respective periods in 2020 (“Q3 2020” and “YTD
Q3 2020”, respectively):

    •    Revenue for Q3 2021 decreased to approximately $15.9 million (Q3 2020 - $16.8 million), representing a
         5.4% decrease. Revenue for YTD Q3 2021 increased to $52.6 million (YTD Q3 2020 - $40.3 million),
         representing a 30.5% increase.

    •    Mining operating income increased by $0.2 million (or 11.8%) to $1.9 million in Q3 2021 (Q3 2020 - $1.7
         million), representing an improved gross margin of 11.9% in Q3 2021 from 9.8% in Q3 2020. Mining
         operating income in YTD Q3 2021 increased by $2.6 million (or 65%) to $6.6 million (YTD Q2 2020 - $4.0
         million), representing an improved gross margin of 12.6% in YTD Q3 2021 from 10.0% in YTD Q3 2020.

    •    Operating loss was $0.4 million in Q3 2021 compared to an operating loss of $0.8 million in Q3 2020.
         Operating loss improved by $1.7 million to $1.4 million in YTD Q3 2021 from $3.1 million in YTD Q3
         2020, a 54.8% decrease in operating loss.

    •    Net loss attributable to shareholders was $2.5 million (loss attributable to shareholders - $0.02 per share) in
         Q3 2021 versus income of $0.2 million in Q3 2020 (earnings attributable to shareholders - $0.00 per share).
         The decrease during Q3 2021 is primarily attributable to an increase in the foreign exchange loss as the South
         African Rand weakened against the U.S. Dollar.

    •    Net income attributable to shareholders increased to $0.8 million (earnings attributable to shareholders -
         $0.01 per share) in YTD Q3 2021 compared to a loss of $11.0 million (loss attributable to shareholders -
         $0.12 per share) in YTD Q3 2020. The improvement during YTD Q3 2021 is mainly attributable to the
         increased revenue and positive gross margins generated by remining and processing the Company’s tailings
         resources at the Crocodile River Mine (“CRM”) to produce chrome concentrate and platinum group metals
         (“PGM”) concentrate, respectively; a decrease in the foreign exchange loss as the South African Rand
         recovered against the U.S. Dollar; and a gain of $3.3 million to settle and dismiss certain outstanding lawsuits
         (see press release of June 21, 2021 for further information).
    •    Positive working capital (current assets less current liabilities) of $13.1 million as at September 30, 2021
         (December 31, 2020 - $4.1 million).

Operations

The Company continues its Retreatment Project at Barplats Mines (Pty) Limited’s tailings facility located at the
Company’s CRM in South Africa.

Summary of chrome production for the three and nine months ended September 30, 2021 and 2020:

                               Q3 2021                Q3 2020               YTD Q3 2021            YTD Q3 2020
 Total Tailings Feed
                               638,791                 622,389                1,906,963              1,657,570
 (Tons)
 Average grade Cr
                               38.77%                  38.66%                  38.57%                  38.58%
 concentrate
 Tons of Cr
                               195,942                 275,816                 623,331                784,778
 concentrate

The Company’s majority of revenue (approximately 96% and 93% for Q3 2021 and YTD Q3 2021, respectively) is
generated from the offtake agreement with Union Goal Offshore Solution Limited (“Union Goal”) in relation to
chrome concentrate production from the Retreatment Project. The remaining amount of the Company’s revenue was
from PGM concentrate sales to Impala Platinum Limited (“Impala”). There were no PGM revenues generated during
the comparable periods in 2020.

The completion of the reconfiguration and optimization of the small-scale PGM circuit (“PGM Circuit D”) in Q1
2021 continued to successfully utilize the feed, following the recovery of chrome concentrate, to produce PGM
concentrate under the respective offtake agreements in Q3 2021. Refurbishment work commenced on the PGM main
plant circuit (“PGM Main Circuit B”) during April 2021 and the circuit was commissioned in October 2021 (see
press release of October 29, 2021 for further information), which is expected to drive further revenue growth and gross
margin improvement.

Summary of PGM production for the three and nine months ended September 30, 2021:

                               Q3 2021                Q3 2020              YTD Q3 2021             YTD Q3 2020
 Tons of PGM
                                 366                       -                     948                      -
 concentrate

Diana Hu, President, Chief Executive Officer, and Director of Eastplats commented, “We continue to be encouraged
by the results from the third quarter as Eastplats continues its positive revenue growth and profitability through the
Retreatment Project; increasing PGM capacity by the recent commissioning of PGM Main Circuit B; and the
possibility to restart the Zandfontein underground operations at the Crocodile River Mine.”

Covid-19

There were no changes to the alert levels in South Africa, and they remain at alert level 1 regarding COVID-19. The
Company continues to follow the health guidelines of the Government of South Africa. The chrome and PGM
production and delivery remains in full operation. The effects of COVID-19 are evolving and changing and the
consequences of a further increase in the alert level in South Africa, temporary shutdown of any operations or other
related issues cannot be reasonably estimated at this time, but could potentially have material adverse effects on the
Company’s business, operations, liquidity and cashflows.
Outlook

The Company’s targets for 2021 were updated following the completion of its rights offering in January 2021,
including:

    •     Continue operating the Retreatment Project efficiently;

    •     Reconfigure, optimize, and consistently operate the PGM Circuit D, which also includes funding for some
          of the initial work required to restart the PGM Main Circuit B (see press release of February 2, 2021)
          (completed);

    •     Completion of the refurbishment of the existing PGM Main Circuit B to increase the capacity and opportunity
          of PGM recovery and sales (see press release of October 29, 2021) (completed);

    •     Completion of the optimization project for the Retreatment Project (ongoing);

    •     Establishment of the second phase of the tailings storage facility (“TSF”) capital works program (ongoing);

    •     Upgrades and repairs to the CRM Zandfontein underground (“Zandfontein Underground”) shaft and rock
          winder to ensure they are available for underground mining operations (rock winder completed and shaft
          repairs expected completion by year end);

    •     Mareesburg project environmental work to complete the legal scan on the environmental impact assessment
          (“EIA”) and other environmental studies and amendments (ongoing);

    •     Prospecting and assessment work in relation to Zandfontein, Crocette and Spitzkop ore bodies (ongoing);

    •     EIA and assessment work regarding a vertical furnace and pelletizer of chrome concentrate (ongoing); and

    •     CRM underground assessment including all chrome recovery activities in relation to the Retreatment Project
          (ongoing).

The Company is actively progressing several revenue opportunities and exploring options to utilize or monetize other
assets. Furthermore, the Company is pursuing funding arrangements to execute the Zandfontein Underground restart
business plan.

The Company has a primary listing on the Toronto Stock Exchange and a secondary listing on the JSE Limited.

The Company has filed the following documents, under the Company’s profile on SEDAR at www.sedar.com:

    •     Condensed interim consolidated financial statements for the three and nine months ended September 30,
          2021; and

    •     Management’s discussion and analysis for the three and nine months ended September 30, 2021.

The condensed interim consolidated financial statements for the three and nine months ended September 30, 2021 is
available for download at https://eastplats.com/investors-2/reports/ and is also available on the JSE’s website at:
https://senspdf.jse.co.za/documents/2021/jse/isse/eps/Q321.pdf.


For further information, please contact:
 EASTERN PLATINUM LIMITED
 Wylie Hui, Chief Financial Officer and Corporate Secretary
 whui@eastplats.com (email)
 (604) 800-8200 (phone)
Cautionary Statement Regarding Forward-Looking Information
This press release contains “forward-looking statements” or “forward-looking information” (collectively referred to herein as
“forward-looking statements”) within the meaning of applicable securities legislation. Such forward-looking statements include,
without limitation, forecasts, estimates, expectations and objectives for future operations that are subject to a number of
assumptions, risks and uncertainties, many of which are beyond the control of the Company. Forward-looking statements are
statements that are not historical facts and are generally, but not always, identified by the words “will”, “plan”, “intends”, “may”,
“could”, “expects”, “anticipates” and similar expressions. Further disclosure of the risks and uncertainties facing the Company and
other forward-looking statements are discussed in the Company’s most recent Annual Information Form available under the
Company’s profile on www.sedar.com.

In particular, this press release contains, without limitation, forward-looking statements pertaining to: profitability; the Company’s
targets for 2021; forecast of operational activity and optimization of the Retreatment Project; estimated operations and production
of PGM Circuit D and PGM Main Circuit B; estimated ramp up or upgrades to the PGM Circuit D and PGM Main Circuit B;
establishment of the second phase of the TSF capital works program; potential additional revenue growth and gross margin
improvement from the PGM Circuit D and PGM Main Circuit B; execution of the Zandfontein Underground restart business plan
and related funding; Mareesburg project environmental work to complete the legal scan on the EIA and other environmental studies
and amendments; prospecting and assessment work in relation to Zandfontein, Crocette and Spitzkop ore bodies; EIA and
assessment work regarding a vertical furnace and pelletizer of chrome concentrate; CRM underground assessment including all
chrome recovery activities in relation to the Retreatment Project; and potential effects of COVID-19 and any future measures taken
by the Government of South Africa and their impact on the Company; and its business, operations, liquidity and cashflows. These
forward-looking statements are based on assumptions made by and information currently available to the Company. Although
management considers these assumptions to be reasonable based on information currently available to it, they may prove to be
incorrect. By their very nature, forward-looking statements involve inherent risks and uncertainties and readers are cautioned not
to place undue reliance on these statements as a number of factors could cause actual results to differ materially from the beliefs,
plans, objectives, expectations, estimates and intentions expressed in such forward-looking statements. These factors include, but
are not limited to, unanticipated problems that may arise in the Company’s production processes, commodity prices, lower than
expected grades and quantities of resources, need for additional funding and availability of such additional funding on acceptable
terms, economic conditions, currency fluctuations, competition and regulations, legal proceedings and risks related to operations
in foreign countries.

All forward-looking statements in this press release are expressly qualified in their entirety by this cautionary statement, the
“Cautionary Statement on Forward-Looking Information” section contained in the Company’s most recent Management’s
Discussion and Analysis available under the Company’s profile on www.sedar.com. The forward-looking statements in this press
release are made as of the date they are given and, except as required by applicable securities laws, the Company disclaims any
intention or obligation, and does not undertake, to update or revise any forward-looking statements, whether as a result of new
information, future events or otherwise.

No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained
herein.

JSE Sponsor
PSG Capital

Date: 11-11-2021 08:45:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.