[OFFICIAL] Anglo American Platinum Limited (Incorporated in the Republic of South Africa) (Registration number: 1946/022452/06) Share Code: AMS ISIN: ZAE000013181 (“The Company" or "Anglo American Platinum") 02 February 2023 Anglo American Platinum Limited PGMs Production Report for the fourth quarter ending 31 December 2022 Overview – Q4 2022 performance against prior period Q4 2021 • Safety performance – continued focus on the elimination of fatalities and safety. No fatalities were recorded at own-managed operations and Joint Operations. A zero harm focus resulted in the lowest recorded injury rate. • Total PGMs production (expressed as 5E+Au metal-in-concentrate) decreased by 10% to 990,400 ounces. • Own-managed mines PGMs production decreased by 12% to 557,600 ounces due to lower grades from Mogalakwena and Unki, and infrastructure closures at Amandelbult, partially offset by a strong performance at Mototolo. • Refined PGMs production (owned production, excluding tolling) decreased by 37% to 877,200 ounces as a result of the delayed Polokwane smelter rebuild, due to the delivery of sub-standard materials for furnace construction. The rebuild was completed at the end of Q4 2022, and by the end of January 2023 the ramp-up was largely completed. • Build-up of work-in-progress inventory at year-end was a net increase of c.100,000 PGM ounces, due to the delay to the Polokwane smelter rebuild, as well as Eskom load-shedding (scheduled power outages), partially offset by strong performance from Waterval and Mortimer smelters. • PGMs sales volumes (from production, excluding sales from trading) decreased by 31% to 883,400 ounces in line with lower refined production. • Guidance for 2023 (unchanged)– Metal-in-concentrate PGM production guidance is 3.6 - 4.0 million ounces. Refined production guidance for 2023 is 3.6-4.0 million ounces. Unit cost guidance per PGM ounce produced is R16,800 - R17,800. [OFFICIAL] Natascha Viljoen, CEO of Anglo American Platinum, said: “Our commitment to eliminating fatalities from our workplaces and achieving zero harm continues to help us keep our people safe. We had no work-related fatalities at our own-managed operations in the period. In addition, continued collaborative efforts with employees, unions, contractors, and other partners have resulted in a material improvement in our total recordable case injury frequency rate (TRCFR), which decreased by 12% to 2.25 per million hours worked. We remain steadfastly focused on ensuring continuous improvement in safety. Total PGM production was 10% lower compared to the prior period as we continued to see lower grades at Mogalakwena. The closure of infrastructure at Amandelbult that came to the end of its life, and maintenance at the Unki concentrator, as well as lower grade and recoveries at Unki also contributed to lower production. This, however, was partially offset by a strong performance from Mototolo, which saw improved ground conditions, leading to an increase in grade. Further stability at the Mototolo plant following the successful concentrator debottlenecking project also led to improved recoveries and production. Refined production of 877,200 PGM ounces was largely impacted due to the delay in the Polokwane smelter rebuild, lower mined production and the impact of Eskom load-shedding. However, this was partially mitigated by strong utilisation and throughput from our other smelters. The Polokwane smelter rebuild was completed in December 2022, and we have largely completed the ramp-up. Sales volumes of 883,400 PGM ounces were in line with refined production. The impact of the delay to the Polokwane smelter rebuild, as well as Eskom load-shedding, net of inventory release and strong performance from Waterval and Mortimer smelters during the year, resulted in a year-end build-up in work- in-progress inventory of c.100,000 PGM ounces. We remain on track to achieve our 2023 guidance, with a strong focus on operational excellence and cost discipline in the coming year.” Anglo American Platinum Q4 2022 Q4 2022 FY 2022 PGM Production Report - Q4 2022 Q4 Q3 Q2 Q1 Q4 vs vs FY FY vs 1 October 2022 - 31 December 2022 2022 2022 2022 2022 2021 Q4 2021 Q3 2022 2022 2021 FY 2021 M&C PGM¹ production (000 ounce)² 990.4 1,046.1 1,031.5 956.0 1,103.4 (10)% (5)% 4,024.0 4,298.7 (6)% Own-managed mines 557.6 587.2 586.7 529.2 634.6 (12) % (5) % 2,260.7 2,436.8 (7) % Joint operations owned volume 99.0 96.0 99.6 93.9 99.7 (1) % 3 % 388.5 421.5 (8) % Joint operations purchase of concentrate 99.0 96.0 99.6 93.9 99.7 (1) % 3 % 388.5 421.5 (8) % Third party purchase of concentrate 234.8 266.9 245.6 239.0 269.4 (13) % (12) % 986.3 1,018.9 (3) % Refined PGM production owned (000 ounce)² 877.2 994.8 1,240.6 718.5 1,391.3 (37)% (12)% 3,831.1 5,138.4 (25)% 4E Toll refined production 173.1 151.3 143.4 154.8 179.5 (4) % 14 % 622.6 673.8 (8) % Total refined production (owned and toll) 1,050.3 1,146.1 1,384.0 873.3 1,570.8 (33) % (8) % 4,453.7 5,812.2 (23) % PGM sales volume from production (000 ounce) 883.4 933.5 1,206.2 838.2 1,285.2 (31)% (5)% 3,861.3 5,214.4 (26)% Trading sales volume3 789.6 403.4 256.0 400.9 272.8 189 % 96 % 1,849.9 770.6 140 % Total sales volume (production and trading) 1,673.0 1,336.9 1,462.2 1,239.1 1,558.0 7 % 25 % 5,711.2 5,985.0 (5) % ¹ PGM is the sum of platinum, palladium, rhodium, iridium, ruthenium, and gold ounces. ² Referencing AAP guidance. 3 Trading sales volume not produced by Anglo American Platinum operations. [OFFICIAL] Review of the quarter Safety We had no work-related fatalities during the period at own-managed operations or Joint Operations. The Total Recordable Case Frequency Rate (TRCFR) per million hours at managed operations of 2.25 per million hours was the lowest recorded injury rate, improving by 12% compared to the prior period of 2.55 per million hours. Significant management efforts are focusing on contractor safety, working collaboratively with our Joint Operations on safety, incorporating learnings to stop repeat incidents and increased management oversight on high-risk work. Through implementing technology in conventional underground operations, including blast-on-mesh and winch-scraper proximity detection, high risk incidents have reduced. Metal-in-concentrate (M&C) PGM production Total PGM production Total PGM production in Q4 2022 decreased 10% against the prior period (Q4 2021) to 990,400 ounces, with platinum production decreasing 10% to 458,500 ounces, and palladium production decreasing by 11% to 307,500 ounces. PGM production from own-managed mines Total PGM production from own-managed mines decreased by 12% to 557,600 ounces (platinum production decreased by 12% to 253,600 ounces, while palladium production decreased by 13% to 200,300 ounces), primarily due to lower production from Mogalakwena, Amandelbult and Unki, partially offset by strong production from Mototolo. PGM production at Mogalakwena decreased by 15% to 256,700 ounces (platinum decreased by 15% to 107,500 and palladium production decreased by 14%, to 118,600 ounces), largely due to a 19% reduction in 4E built-up head grade to 2.62g/t from 3.22g/t in Q4 2021. The decline in the grade is a factor of mining in lower grade areas, as well as lower than anticipated grade mined in some areas. Since late 2021, there has been an extensive drilling program together with improved geological modelling, that was concluded at the end of 2022. This has translated into changes in the near-term ounce profile. This short-term change is not expected to affect the overall Mineral Resource estimation. PGM production from Amandelbult decreased by 17% to 176,600 ounces (platinum production decreased by 17% to 89,600 ounces and palladium production decreased by 18% to 40,800 ounces), mainly due to the closure of Tumela Upper conventional infrastructures, the closure of current open-pit operations, as well as poor ground conditions at Dishaba. The Merensky concentrator was closed in Q4 2022, and greater efficiency benefits will be achieved through utilising the lower cost UG1 and UG2 concentrators at Amandelbult. Mototolo PGM production increased by 26% to 71,700 ounces (platinum production increased by 27% to 32,800 ounces and palladium increased by 27% to 20,600 ounces), largely due to increased throughput supported by a 7% increase in 4E built-up head grade to 3.22g/t, due to grade improvement initiatives and increased recoveries at the concentrator following increased stability of the concentrator debottlenecking project. Unki PGM production decreased by 17% to 52,600 ounces (platinum production decreased by 15% to 23,700 ounces and palladium production decreased by 18% to 20,300 ounces). Unki was impacted by maintenance at the concentrator, as well as lower grade and recovery. [OFFICIAL] PGM production from Joint Operations (50% own-mined production and 50% purchase of concentrate) Total PGM production from Joint Operations was broadly in line compared to Q4 2021 at 198,000 ounces (platinum production of 90,600 ounces and palladium production of 58,400 ounces). Total Modikwa PGM production decreased by 2% to 71,600 ounces (platinum production was flat at 28,800 ounces and palladium production decreased 3% to 26,800 ounces). While tonnes milled increased by 9%, 4E built-up head grade decreased by 6% as higher proportions of lower grade Merensky ore and surface material were milled. Total Kroondal PGM production was flat at 126,400 ounces (platinum production increased by 2% to 61,800 ounces and palladium production decreased by 1% to 31,600 ounces) despite the gradual ramp-down at Simunye shaft, which benefited the prior period, and geologically challenging ground across the complex, which was offset by open pit mining which commenced during 2022. Purchases of PGM concentrate from third parties Purchases of PGM concentrate (POC) from third parties decreased by 13% to 234,800 ounces (platinum POC decreased by 15% to 114,300 ounces and palladium POC decreased by 14% to 49,000 ounces), due to lower receipts from third parties. Refined PGM production Refined PGM production (from owned production, excluding tolling) decreased by 37% to 877,200 ounces, mainly due to the rebuild of Polokwane smelter, which had been delayed in October 2022 due to the delivery of sub-standard materials, lower M&C receipts, as well as the prior period being higher than normal as built-up inventory from the ACP rebuild was processed. Refined platinum production decreased by 40% to 391,200 ounces and refined palladium production decreased by 34% to 278,500 ounces. The reduction in refined production was partially mitigated by strong utilisation and throughput from our other smelters, Waterval and Mortimer, helping to release some of the built-up inventory. The Polokwane smelter rebuild was completed in December 2022, with ramp-up largely completed in January. The impact of the delay to the Polokwane smelter rebuild, as well as Eskom load-shedding, net of inventory release and strong performance from Waterval and Mortimer smelters during the year, resulted in a year-end build-up in work-in- progress inventory of c.100,000 PGM ounces. Toll-refined PGM production decreased by 4% to 173,100 PGM ounces. Base metal production Nickel production decreased by 16% to 4,800 tonnes and copper production decreased by 5% to 3,800 tonnes. PGM sales volumes PGM sales volumes (excluding trading) decreased by 31% to 883,400 ounces, in line with lower refined production. Platinum sales volumes decreased by 40% to 382,100 ounces and palladium sales volumes decreased by 29% to 282,200 ounces. The average Q4 2022 realised basket price of $2,293/PGM ounce was lower than Q4 2021 due to lower rhodium, iridium, and ruthenium prices. [OFFICIAL] 2023 Guidance (unchanged) Metal-in-concentrate (M&C) PGM guidance for 2023 is 3.6 - 4.0 million PGM ounces(1). Refined PGM production guidance is 3.6 - 4.0 million PGM ounces, subject to the impact of Eskom load-shedding. Unit cost guidance for 2023 is R16,800 - R17,800 per PGM ounce. (1) Metal in concentrate production is expected to be 1.65 – 1.85 million ounces of platinum, 1.15 – 1.25 million ounces of palladium, and 0.8 – 0.9 million ounces of other PGMs and gold. [OFFICIAL] Anglo American Platinum Q4 2022 Q4 2022 FY 2022 PGM Production Report - Q4 2022 Q4 Q3 Q2 Q1 Q4 vs vs FY FY vs 1 October 2022 - 31 December 2022 2022 2022 2022 2022 2021 Q4 2021 Q3 2022 2022 2021 FY 2021 Safety Fatalities - own managed operations4 number 0 0 0 0 1 0 1 Total recordable injury frequency rate /million 2.25 2.35 2.60 2.16 2.55 (12) % (4) % 2.34 2.60 (10) % Total M&C PGM production 000 oz 990.4 1,046.1 1,031.5 956.0 1,103.4 (10) % (5)% 4,024.0 4,298.7 (6)% Platinum 000 oz 458.5 478.9 479.1 444.3 511.2 (10) % (4) % 1,860.8 1,986.6 (6) % Palladium 000 oz 307.5 323.8 321.5 296.6 345.2 (11) % (5) % 1,249.4 1,352.7 (8) % Tonnes milled 000 7,021 7,042 7,050 6,609 7,217 (3) % — % 27,721 28,205 (2) % 4E Built-up head grade g/t 3.19 3.33 3.33 3.24 3.49 (9) % (4) % 3.27 3.50 (6) % Own mined volume Total mined production Total M&C PGM production 000 oz 656.6 683.2 686.3 623.1 734.3 (11) % (4)% 2,649.2 2,858.3 (7)% Platinum 000 oz 298.9 308.8 314.1 283.8 332.4 (10) % (3) % 1,205.6 1,296.3 (7) % Palladium 000 oz 229.4 240.0 240.9 219.3 258.6 (11) % (4) % 929.6 1,015.9 (8) % Tonnes milled 000 7,021 7,042 7,050 6,609 7,217 (3) % — % 27,721 28,205 (2) % 4E Built-up head grade g/t 3.19 3.33 3.33 3.24 3.49 (9) % (4) % 3.27 3.50 (6) % Own managed mines Total M&C PGM production 000 oz 557.6 587.2 586.7 529.2 634.6 (12) % (5)% 2,260.7 2,436.8 (7)% Platinum 000 oz 253.6 265.4 268.6 241.0 287.7 (12) % (4) % 1,028.6 1,107.3 (7) % Palladium 000 oz 200.3 211.5 211.7 191.6 229.1 (13) % (5) % 815.1 891.1 (9) % Tonnes milled 000 6,175 6,224 6,208 5,789 6,391 (3) % (1) % 24,396 24,740 (1) % 4E Built-up head grade g/t 3.14 3.30 3.30 3.21 3.48 (10) % (5) % 3.24 3.47 (7) % Mogalakwena mine Total M&C PGM production 000 oz 256.7 259.3 261.4 248.8 300.8 (15) % (1)% 1,026.2 1,214.6 (16)% Platinum 000 oz 107.5 107.6 110.7 104.4 126.2 (15) % — % 430.2 512.1 (16) % Palladium 000 oz 118.6 121.4 121.6 114.5 138.1 (14) % (2) % 476.1 560.7 (15) % Tonnes milled 000 3,659 3,518 3,362 3,315 3,533 4 % 4 % 13,855 14,203 (2) % 4E Built-up head grade g/t 2.62 2.84 2.91 2.81 3.22 (19) % (7) % 2.79 3.23 (14) % Amandelbult mine Total M&C PGM production 000 oz 176.6 192.6 183.4 159.9 213.6 (17) % (8)% 712.5 773.2 (8)% Platinum 000 oz 89.6 96.5 93.4 81.4 107.7 (17) % (7) % 360.8 391.5 (8) % Palladium 000 oz 40.8 44.8 42.5 37.1 49.9 (18) % (9) % 165.2 180.0 (8) % Tonnes milled 000 1,222 1,339 1,504 1,203 1,639 (25) % (9) % 5,268 5,925 (11) % 4E Built-up head grade g/t 4.59 4.47 3.89 4.20 4.18 10 % 3 % 4.27 4.18 2 % Unki mine Total M&C PGM production 000 oz 52.6 59.9 66.3 53.3 63.3 (17) % (12)% 232.1 204.6 13 % Platinum 000 oz 23.7 26.8 29.7 24.5 28.0 (15) % (12) % 104.7 91.1 15 % Palladium 000 oz 20.3 23.3 25.7 20.3 24.9 (18) % (13) % 89.6 80.2 12 % Tonnes milled 000 587 650 625 630 599 (2) % (10) % 2,492 2,091 19 % 4E Built-up head grade g/t 3.24 3.31 3.87 3.26 3.59 (10) % (2) % 3.42 3.52 (3) % Mototolo mine Total M&C PGM production 000 oz 71.7 75.4 75.6 67.2 56.9 26 % (5)% 289.9 244.4 19 % Platinum 000 oz 32.8 34.5 34.7 30.7 25.9 27 % (5) % 132.7 112.7 18 % Palladium 000 oz 20.6 22.0 21.9 19.7 16.2 27 % (6) % 84.2 70.2 20 % Tonnes milled 000 706 716 718 642 620 14 % (1) % 2,782 2,521 10 % 4E Built-up head grade g/t 3.22 3.39 3.39 3.38 3.00 7 % (5) % 3.34 3.14 6 % Joint operations mined production Total M&C PGM production 000 oz 99.0 96.0 99.6 93.9 99.7 (1)% 3 % 388.5 421.5 (8)% Platinum 000 oz 45.3 43.4 45.5 42.8 44.7 1 % 4 % 177.0 189.0 (6) % Palladium 000 oz 29.2 28.6 29.2 27.6 29.5 (1) % 2 % 114.5 124.8 (8) % Tonnes milled 000 846 819 841 819 827 2 % 3 % 3,325 3,465 (4) % 4E Built-up head grade g/t 3.57 3.58 3.53 3.49 3.62 (1) % — % 3.54 3.66 (3) % Modikwa mine Total M&C PGM production 000 oz 35.8 37.6 36.8 34.3 36.4 (2)% (5)% 144.5 146.4 (1)% Platinum 000 oz 14.4 15.0 14.8 13.5 14.4 — % (4) % 57.7 57.5 — % Palladium 000 oz 13.4 14.1 13.8 12.8 13.8 (3) % (5) % 54.1 55.2 (2) % Tonnes milled 000 321 327 308 287 294 9 % (2) % 1,243 1,177 6 % 4E Built-up head grade g/t 3.54 3.69 3.71 3.67 3.76 (6) % (4) % 3.65 3.84 (5) % Kroondal mine Total M&C PGM production 000 oz 63.2 58.4 62.8 59.6 63.4 — % 8 % 244.0 275.1 (11)% Platinum 000 oz 30.9 28.5 30.7 29.3 30.3 2 % 8 % 119.3 131.5 (9) % Palladium 000 oz 15.8 14.5 15.4 14.8 15.9 (1) % 9 % 60.4 69.7 (13) % Tonnes milled 000 525 492 533 532 533 (2) % 7 % 2,082 2,288 (9) % 4E Built-up head grade g/t 3.60 3.51 3.43 3.40 3.54 1 % 3 % 3.48 3.57 (3) % [OFFICIAL] Anglo American Platinum Q4 2022 Q4 2022 FY 2022 PGM Production Report - Q4 2022 Q4 Q3 Q2 Q1 Q4 vs vs FY FY vs 1 October 2022 - 31 December 2022 2022 2022 2022 2022 2021 Q4 2021 Q3 2022 2022 2021 FY 2021 Purchase of concentrate Total purchase of concentrate PGM production 000 oz 333.8 362.9 345.2 332.9 369.1 (10)% (8)% 1,374.8 1,440.4 (5)% Platinum 000 oz 159.6 170.1 165.0 160.5 178.8 (11) % (6) % 655.2 690.3 (5) % Palladium 000 oz 78.1 83.8 80.6 77.3 86.6 (10) % (7) % 319.8 336.8 (5) % Joint operations purchase of concentrate PGM production 000 oz 99.0 96.0 99.6 93.9 99.7 (1)% 3 % 388.5 421.5 (8)% Platinum 000 oz 45.3 43.4 45.5 42.8 44.7 1 % 4 % 177.0 189.0 (6) % Palladium 000 oz 29.1 28.6 29.2 27.6 29.5 (1) % 2 % 114.5 124.8 (8) % Third party purchase of concentrate PGM production 000 oz 234.8 266.9 245.6 239.0 269.4 (13)% (12)% 986.3 1,018.9 (3)% Platinum 000 oz 114.3 126.7 119.5 117.7 134.1 (15) % (10) % 478.2 501.3 (5) % Palladium 000 oz 49.0 55.2 51.4 49.7 57.1 (14) % (11) % 205.3 212.0 (3) % Refined PGM production - owned PGM ounces 000 oz 877.2 994.8 1,240.6 718.5 1,391.3 (37)% (12)% 3,831.1 5,138.4 (25)% Platinum 000 oz 391.2 457.2 600.4 334.1 653.5 (40) % (14) % 1,782.9 2,399.9 (26) % Palladium 000 oz 278.5 317.1 374.8 228.1 423.2 (34) % (12) % 1,198.5 1,627.5 (26) % Rhodium 000 oz 51.7 64.8 86.4 46.3 97.7 (47) % (20) % 249.2 349.3 (29) % Minor PGMs and gold 000 oz 155.8 155.7 179.0 110.0 216.9 (28) % — % 600.5 761.7 (21) % Base metal production - owned Nickel tonnes 4,800 5,700 6,200 4,600 5,700 (16) % (16) % 21,300 22,300 (4) % Copper tonnes 3,800 3,900 3,900 3,400 4,000 (5) % (3) % 15,000 14,600 3 % Chrome 000 t 213 235 203 181 192 11 % (10) % 831 893 (7) % Toll refined production Total 4E toll refined production 000 oz 173.1 151.3 143.4 154.8 179.5 (4)% 14 % 622.6 673.8 (8)% Platinum 000 oz 102.5 89.5 85.9 91.2 106.8 (4) % 15 % 369.2 403.3 (8) % Palladium 000 oz 54.2 46.9 44.2 46.6 55.2 (2) % 16 % 191.8 205.9 (7) % PGM Sales volume from production PGM ounces 000 oz 883.4 933.5 1,206.2 838.2 1,285.2 (31)% (5)% 3,861.3 5,214.4 (26)% Platinum 000 oz 382.1 414.6 600.9 333.3 632.9 (40) % (8) % 1,730.9 2,367.3 (27) % Palladium 000 oz 282.2 302.0 388.8 235.8 395.1 (29) % (7) % 1,208.8 1,589.5 (24) % Trading sales volume5 PGM ounces 000 oz 789.6 403.4 256.0 400.9 272.8 189 % 96 % 1,849.9 770.6 140 % Platinum 000 oz 667.8 281.2 108.9 231.2 175.3 281 % 137 % 1,289.1 409.4 215 % Palladium 000 oz 107.6 115.5 138.8 147.0 84.8 27 % (7) % 508.9 318.3 60 % Realised prices and exchange rate Platinum (US$/oz 1,051 877 946 998 986 7 % 20 % 962 1,083 (11) % Palladium (US$/oz) 1,975 2,024 2,178 2,097 1,971 — % (2) % 2,076 2,439 (15) % Rhodium (US$/oz) 13,373 14,215 17,110 17,161 13,788 (3) % (6) % 15,600 19,613 (20) % Iridium (US$/oz) 3,564 3,885 4,677 3,874 3,792 (6) % (8) % 3,939 4,765 (17) % Ruthenium (US$/oz) 413 485 573 476 530 (22) % (15) % 483 433 12 % Gold (US$/oz) 1,740 1,702 1,858 1,873 1,791 (3) % 2 % 1,786 1,788 — % Average FX achieved on sales ZAR/US) 17.60 17.15 15.58 15.16 15.43 14 % 3 % 16.31 14.71 11 % US$ basket price per PGM ounce $ (US$/oz 2,293 2,531 2,661 2,685 2,434 (6) % (9) % 2,551 2,761 (8) % ZAR basket price per PGM ounce (ZAR/oz) 40,108 43,426 41,601 40,458 37,500 7 % (8) % 41,453 40,511 2 % US$ basket price per Platinum ounce (US$/oz) 5,300 5,699 5,342 6,753 4,943 7 % (7) % 5,690 6,082 (6) % ZAR basket price per Platinum ounce (ZAR/oz) 92,717 97,780 83,510 101,752 76,152 22 % (5) % 92,473 89,233 4 % 4 The tragic fatality of Mr Julian Sesinyi was retrospectively ) recorded on the date of his accident which was on 23 November 2021. 5 Trading sales volume - not produced by Anglo American Platinum operations. [OFFICIAL] Sponsor: Merrill Lynch South Africa (Pty) Ltd t/a BofA Securities For further information, please contact: Investors: Media: Emma Chapman Nomonde Ndwalaza (SA) +27 (0) 11 373 6239 (SA) +27 (0) 11 638 0228 emma.chapman@angloamerican.com nomonde.ndwalaza@angloamerican.com Notes to editors: Anglo American Platinum Limited is a member of the Anglo American plc Group and is a leading primary producer of platinum group metals. The company is listed on the Johannesburg Securities Exchange (JSE). Its mining, smelting and refining operations are based in South Africa. Elsewhere in the world, the Group owns Unki Platinum Mine and smelter in Zimbabwe. Anglo American Platinum has two joint operations with several historically disadvantaged South African consortia as part of its commitment to the transformation of the mining industry. Anglo American Platinum is committed to the highest standards of safety and continues to make a meaningful and sustainable difference in the development of the communities around its operations. www.angloamericanplatinum.com Anglo American is a leading global mining company and our products are the essential ingredients in almost every aspect of modern life. Our portfolio of world-class competitive operations, with a broad range of future development options, provides many of the future-enabling metals and minerals for a cleaner, greener, more sustainable world and that meet the fast growing every day demands of billions of consumers. With our people at the heart of our business, we use innovative practices and the latest technologies to discover new resources and to mine, process, move and market our products to our customers – safely and sustainably. As a responsible producer of diamonds (through De Beers), copper, platinum group metals, premium quality iron ore and steelmaking coal, and nickel – with crop nutrients in development – we are committed to being carbon neutral across our operations by 2040. More broadly, our Sustainable Mining Plan commits us to a series of stretching goals to ensure we work towards a healthy environment, creating thriving communities and building trust as a corporate leader. We work together with our business partners and diverse stakeholders to unlock enduring value from precious natural resources for the benefit of the communities and countries in which we operate, for society as a whole, and for our shareholders. Anglo American is re-imagining mining to improve people’s lives. www.angloamerican.com