Try our mobile app

Quarterly Activities Report

Published: 2023-07-20 09:15:29 ET
<<<  go to JSE:BHG company page
BHP Group Limited
BHP Group Limited ABN 49 004 028 077
Registered in Australia
Registered Office: Level 18, 171 Collins Street Melbourne VIC 3000
Share code: BHG
ISIN: AU000000BHP4


Release Time                 IMMEDIATE
Date                         20 July 2023
Release Number               13/23

BHP OPERATIONAL REVIEW
FOR THE YEAR ENDED 30 JUNE 2023
•    There were two fatalities during the financial year. We are committed to sharing the learnings from
     these tragic events and remain resolute in our commitment to eliminating fatalities and serious injuries
     at BHP.
•    Full year production guidance was achieved for copper, iron ore, metallurgical coal and energy coal.
     Nickel achieved revised guidance and finished in line with the lower end of original guidance.
•    Annual production records at Western Australia Iron Ore (WAIO) of 285 Mt (100% basis), Spence of 240 kt,
     and Olympic Dam for both copper of 212 kt and refined gold of 186 troy koz.
•    Full year unit cost guidance1 is expected to be achieved at Escondida, WAIO and New South Wales
     Energy Coal (NSWEC). BHP Mitsubishi Alliance (BMA) is expected to be marginally above its revised
     guidance range.
•    Average realised prices for copper, iron ore and metallurgical coal products were lower in the 2023
     financial year compared to the prior year. Nickel prices remained stable, while thermal coal prices were
     stronger, predominantly in the first half.
•    BHP completed the acquisition of OZ Minerals Ltd (OZL) on 2 May 20232.
•    BHP has continued to make strong progress at Oak Dam in South Australia. We have defined an
     Exploration Target3 and plan to increase the number of exploration drills from nine to eleven by the
     end of the 2023 calendar year.
•    In Australia, BHP released its sixth Reconciliation Action Plan, which was awarded Elevate status.

BHP Chief Executive Officer, Mike Henry:
“The financial year was marked by the deaths of Jody Byrne and Nathan Scholz. These tragic events underscore the
absolute importance of safety and we are resolute in our commitment to eliminating fatalities and serious injuries at
BHP.

“BHP finished the year with a strong fourth quarter, increasing annual production across the board and achieving
annual records at WAIO, Olympic Dam and Spence. WAIO shipped record volumes on the back of productivity in its
supply chain, rail network and car dumpers, while South Flank completed its deployment of autonomous haul trucks
in May and is on track to ramp up to full production in the next 12 months. Olympic Dam’s improved reliability and
productivity delivered record annual output in copper, gold and silver, and the integration of OZ Minerals into our
South Australian copper business is expected to lift production to between 310 and 340 kt in FY24. At Escondida,
the team managed through operational challenges to deliver solid production and position the asset to increase
output further in FY24. Our Queensland coal operations achieved strong underlying performance including the
transition to autonomous fleets at Goonyella Riverside and Daunia, offsetting the impact of significant wet weather.

“Inflationary pressures impacted our business in the year, and we remain laser focused on safety and productivity to
remain competitive. Competitiveness will be ever more important as we enter the new financial year and at a time
when there are new challenges and opportunities to resource development and global economic volatility.

“BHP’s portfolio is geared towards high quality steelmaking and growth options in future facing commodities. The
Jansen potash project in Canada remains ahead of plan and studies for Stage 2 are progressing. Through the year,
BHP made strategic investments and exploration progress in copper and nickel prospects globally, including
Kabanga in Tanzania, Oak Dam in Australia, Filo Mining with the Filo del Sol project in Argentina and Chile, and
Ocelot in the United States, as well as Serbia and Peru.”


BHP Operational Review for the year ended 30 June 2023                                                             1
Summary
Operational performance
Production and guidance are summarised below.
                                                                             FY23        Jun Q23        Jun Q23
                                                                   Jun         vs             vs             vs                 FY24               FY24e
Production                                           FY23          Q23       FY22        Jun Q22        Mar Q23             guidance             vs FY23
Copper (kt)i                                       1,716.5       476.2         9%              3%            17%       1,720 – 1,910           0% – 11%
      Escondida (kt)                                1055.3       293.0         5%              1%            16%       1,080 – 1,180           2% – 12%
      Pampa Norte (kt)                               288.8         68.5        3%           (11%)            (6%)          210 – 250 ii
                                                                                                                                           (27%) – (13%)
      Copper South Australia (kt)iii                 232.4         76.6       68%             38%            48%           310 – 340          33% – 46%
      Antamina (kt)                                  138.4         36.5       (8%)           (8%)            23%           120 – 140          (13%) – 1%
      Carajás (kt)                                     1.6          1.6           -               -              -                   -                   -
Iron ore (Mt)                                        257.0         65.3        1%              2%             9%         254 – 264.5           (1%) – 3%
      WAIO (Mt)                                      252.5         64.1        1%              1%             9%           250 – 260           (1%) – 3%
      WAIO (100% basis) (Mt)                         285.3         72.7        1%              1%            10%           282 – 294           (1%) – 3%
      Samarco (Mt)                                     4.5          1.2       11%             22%            17%               4 – 4.5        (11%) – 0%
Metallurgical coal - BMA (Mt)                         29.0          8.5        0%              4%            22%              28 – 31          (4%) – 7%
      BMA (100% basis) (Mt)                           58.0         17.0        0%              4%            22%              56 – 62          (4%) – 7%
Energy coal – NSWEC (Mt)                              14.2          4.8        3%             22%            21%              13 – 15          (8%) – 6%
Nickel (kt)                                           80.0         22.0        4%             17%            12%              77 – 87          (4%) – 9%
i.        Includes contribution of 21.5 kt from operations acquired from OZL2.
ii.       Production guidance for FY24 is provided for Spence only. Cerro Colorado is expected to produce ~9 kt as it transitions to closure by
          31 December 2023.
iii.      Comprised of Olympic Dam, Prominent Hill and Carrapateena. Refer to the production and sales report for more details.



                                           FY23         Jun Q23
Production                             (vs FY22)   (vs Mar Q23) Jun Q23 vs Mar Q23 commentary
Copper (kt)                              1,716.5             476.2 Higher concentrate volumes at Escondida reflect the higher concentrate feed
                                             9%               17% grade of 0.93 per cent, and higher volumes at Copper South Australia resulted in
                                                                   a BHP record for quarterly production from the refinery at Olympic Dam, and
                                                                   reflect the addition of Prominent Hill and Carrapateena.
Iron ore (Mt)                              257.0              65.3 Increased production at WAIO, despite unfavourable impacts from Tropical Cyclone
                                             1%                9% Ilsa, due to strong supply chain performance and the prior period impacts from the
                                                                   temporary shutdown of operations following the fatality, as well as the tie-in activity
                                                                   of the Port Debottlenecking Project 1 (PDP1).
Metallurgical coal (Mt)                     29.0               8.5 Increased production driven by increased yield, improved truck productivity and
                                             0%               22% favourable weather conditions, partially offset by the commencement of a second
                                                                   longwall move at Broadmeadow.
Energy coal (Mt)                            14.2               4.8 Higher volumes as a result of additional stripping volumes, decreased proportion
                                             3%               21% of washed coal, favourable weather conditions, and improvement in truck
                                                                   productivity with record quarterly annualised truck hours.
Nickel (kt)                                 80.0              22.0 Higher volumes due to improved mining performance at Mt Keith, increased third
                                             4%               12% party purchases and inventory drawdowns enabling increased concentrate
                                                                   production, partially offset by a heavy rain event in April 2023.




BHP Operational Review for the year ended 30 June 2023                                                                                                       2
Summary of disclosures
BHP expects its financial results for the second half of the 2023 financial year to reflect certain items summarised in
the table below. The table does not provide a comprehensive list of all items impacting the period. The financial
statements are the subject of ongoing work that will not be finalised until the release of the financial results on
22 August 2023. Accordingly, the table below contains preliminary information that is subject to update and finalisation.
                                                                                                                H2 FY23
                                                                                                                 impact
Description                                                                                                       US$Mi             Classificationii
For the 2023 financial year, unit costs at Escondida and WAIO are expected to be towards the                             -        ↑ Operating costs
upper end of guidance ranges, and unit costs at NSWEC are expected to be in line with the
revised guidance range (at guidance exchange rates)
Unit costs at BMA are expected to be marginally above the revised guidance range (at guidance
exchange rates)
Note: Australian dollar and Chilean peso were weaker than guidance rates in the periodiii
Unit costs will not include any costs relating to the review of employee entitlements and
allowances.
Review of employee entitlements and allowances                                                                      ~280        ↑ Operating costs –
                                                                                                                             Group and Unallocated
Transaction and integration costs associated with the OZL acquisition                                         ~100 – 150        ↑ Operating costs -
                                                                                                                             Group and Unallocated
Increase to depreciation and amortisation expense relative to H1 FY23, predominantly at WAIO,                 ~100 – 200            ↑ Depreciation,
and includes the contribution of the OZL assets acquired during the period.                                                        amortisation and
                                                                                                                                       impairments
The Group’s adjusted effective tax rate for the 2023 financial year is expected to be in the lower half                  -        Taxation expense
of the guidance range of 30 to 35 per cent
Working capital decrease relating to net price impacts, and provisions relating to employee                  950 – 1,050      ↑ Operating cash flow
entitlements and allowances
Decrease in cash tax paid relative to H1 FY23                                                              1,600 – 1,700      ↑ Operating cash flow
Gross dividends received from equity-accounted investments                                                          ~250       ↑ Investing cash flow
Capital and exploration spend is expected to be approximately US$7.1 bn, below full year                                 -     ↑ Investing cash flow
guidance of approximately US$7.6 bn, primarily driven by favourable FX
Gross dividends paid to non-controlling interests                                                                   ~650      ↓ Financing cash flow
Payment of the H1 FY23 dividend                                                                                   ~4,600      ↓ Financing cash flow
Acquisition of OZL                                                                                                ~6,000       ↓ Investing cash flow
Net debt acquired through OZL acquisition                                                                         ~1,000                   ↑ Net debt
The Group’s net debt balance at 30 June 2023 is expected to be between US$11 and US$11.5 bn                              -                  Net debt
and is expected to remain towards the upper end of our target range of US$5 to US$15 bn in the
near term
Financial impact on BHP Brasil of the Samarco dam failure                                                 Refer footnoteiv         Exceptional item
The financial impact is expected to primarily relate to amortisation of discounting on the provision
and the impact of foreign exchange
Revaluation of deferred tax balances following the substantive enactment of the                              ~250 – 300v           Exceptional item
Chilean Royalty Bill
i     Numbers are not tax effected and comparisons are against the 31 December 2022 financial results, unless otherwise noted.
ii    There will be a corresponding balance sheet, cash flow and/or income statement impact as relevant, unless otherwise noted.
iii   Average exchange rates for FY23 of AUD/USD 0.67 (guidance rate AUD/USD 0.72) and USD/CLP 864 (guidance rate USD/CLP 830).
iv    Financial impact is the subject of ongoing work and is not yet finalised. See Iron ore section for further information on Samarco.
v     To reflect an increase to the mining tax rates in Chile.




BHP Operational Review for the year ended 30 June 2023                                                                                              3
Average realised prices
The average realised prices achieved for our major commodities are summarised below.
                                                                                                              FY23       H2 FY23       H2 FY23
                                                                                                                vs            vs            vs
Average realised pricesi                         H2 FY23        H1 FY23           FY23         FY22           FY22       H2 FY22       H1 FY23
Copper (US$/lb)ii                                     3.80          3.49           3.65         4.16         (12%)           (5%)            9%
Iron ore (US$/wmt, FOB)                              99.88         85.46          92.54       113.10         (18%)          (11%)          17%
Metallurgical coal (US$/t)                         273.08         268.73         271.05       347.10         (22%)          (36%)            2%
                                 iii
      Hard coking coal (US$/t)                     276.22         270.65         273.59       366.82         (25%)          (37%)            2%
      Weak coking coal (US$/t)iii                  250.38         252.12         251.13       296.51         (15%)          (35%)          (1%)
Thermal coal (US$/t)iv                             157.21         354.30         236.51       216.78            9%          (48%)         (56%)
Nickel metal (US$/t)                               23,652         24,362         24,021       23,275            3%          (14%)          (3%)
i      Based on provisional, unaudited estimates. Prices exclude sales from equity accounted investments, third party product and internal sales,
       and represent the weighted average of various sales terms (for example: FOB, CIF and CFR), unless otherwise noted. Includes the impact
       of provisional pricing and finalisation adjustments.
ii     Does not include sales from assets acquired through the purchase of OZL.
iii    Hard coking coal (HCC) refers generally to those metallurgical coals with a Coke Strength after Reaction (CSR) of 35 and above, which
       includes coals across the spectrum from Premium Coking to Semi Hard Coking coals, while weak coking coal (WCC) refers generally to
       those metallurgical coals with a CSR below 35.
iv     Export sales only. Includes thermal coal sales from metallurgical coal mines.

The large majority of iron ore shipments were linked to index pricing for the month of shipment, with price differentials
predominantly a reflection of market fundamentals and product quality. Iron ore sales for the June 2023 half year
were based on an average moisture rate of 6.6 per cent. The large majority of metallurgical coal and energy coal
exports were linked to index pricing for the month of scheduled shipment or priced on the spot market at fixed or
index-linked prices, with price differentials reflecting product quality. The large majority of copper cathodes sales
were linked to index price for quotation periods one month after month of shipment, and three to four months after
month of shipment for copper concentrates sales with price differentials applied for location and treatment costs.
At 30 June 2023, the Group had 342 kt of outstanding copper sales that were revalued at a weighted average price
of US$3.77 per pound. The final price of these sales will be determined in the 2024 financial year. In addition, 354 kt
of copper sales from the 2022 financial year were subject to a finalisation adjustment in the 2023 financial year. The
provisional pricing and finalisation adjustments will decrease Underlying EBITDA by US$243 million in the 2023
financial year and are included in the average realised copper price in the above table.

Corporate update
BHP released its sixth Reconciliation Action Plan in June 2023, which has been recognised with ‘Elevate’ status from
Reconciliation Australia. Some examples of the commitments made in the plan include increasing Indigenous
representation across our Australian workforce to a target of 9.7 per cent by the end of the 2027 financial year, and
a target to achieve an A$1.5 billion spend with Traditional Owner and Indigenous businesses in aggregate across
our Australian assets.

Portfolio
On 2 May 2023, BHP announced the completion of the OZL acquisition. The acquisition strengthens BHP’s portfolio
in copper, nickel and uranium and is in line with our strategy to pursue value adding growth in future facing
commodities. The cash payment by BHP was funded using a combination of BHP’s existing cash reserves and the
proceeds of a debt facility.
In June 2023, BHP agreed to invest an additional C$30 million in Filo Mining Corp via a private placement. The
proceeds from BHP’s investment will be used by Filo for exploration and development of the Filo del Sol project,
located in San Juan Province, Argentina and adjacent Region III in Chile, and for working capital and general
corporate purposes.

Decarbonisation
In the June 2023 quarter, BHP held a briefing updating on its progress and plans to achieve its medium and long-term
operational decarbonisation target and goal and released two Prospects updates on the Pathways to decarbonisation
which are available on the BHP website: The many, many roads to Paris and the electric smelting furnace.



BHP Operational Review for the year ended 30 June 2023                                                                                         4
Copper

Production
                                                                                         FY23     Jun Q23     Jun Q23
                                                                                           vs          vs          vs
                                                                FY23     Jun Q23         FY22     Jun Q22     Mar Q23
Copper (kt)                                                   1,716.5       476.2         9%           3%         17%
Zinc (t)                                                      125,048      38,822         1%          41%         64%
Uranium (t)                                                     3,406         813        43%           5%         (2%)

Copper – Total copper production increased by nine per cent to 1,717 kt. Production for the 2024 financial year is
expected to be between 1,720 and 1,910 kt.
Escondida copper production increased by five per cent to 1,055 kt primarily due to higher concentrator feed grade
of 0.82 per cent, compared to 0.78 per cent in the 2022 financial year. The positive impact of the higher grade was
partially offset by the impact of road blockades across Chile in the December 2022 quarter, which reduced availability
of some key mine supplies. Full year production came in at the low end of revised guidance largely as a result of
measures implemented to manage geotechnical events in a high grade section of the Escondida pit. These included
a resequencing of the mine plan, resulting in lower than anticipated volumes of mined ore and increased processing
of lower grade stockpiles through the concentrators. Production is expected to increase to between 1,080 and
1,180 kt for the 2024 financial year and reflects both an expected increase in concentrator feed grade and an
expected increase in concentrator throughput compared to the 2023 financial year.
Pampa Norte copper production increased by three per cent to 289 kt including a record 240 kt at Spence and 49 kt
at Cerro Colorado. This was largely a result of higher concentrator throughput at the Spence Growth Option (SGO),
partially offset by lower production at Cerro Colorado as it transitions towards closure. The concentrator plant
modifications, which commenced in August 2022, remain on track to be completed in the 2023 calendar year.
Expected capital expenditure for the concentrator modification works remains unchanged at approximately
US$100 million. Production for Spence is expected to be between 210 and 250 kt for the 2024 financial year, with
planned higher concentrator grade and concentrator throughput but lower stacking grade for cathodes. Cerro
Colorado continues to transition towards planned closure by December 2023, with production for the six months until
closure expected to be approximately 9 kt. We are continuing to closely monitor previously identified Spence Tailings
Storage Facility anomalies.
Following the completion of the acquisition of OZL, we have established the Copper South Australia business.
Production from Copper South Australia was 232 kt, comprised of full year production from Olympic Dam of 212 kt
and two months of production2 from Prominent Hill and Carrapateena of 8 kt and 12 kt respectively. Olympic Dam
delivered record BHP copper production as a result of continued strong concentrator and smelter performance
following the major smelter maintenance campaign (SCM21) in the prior year. Record annual gold and silver
production was also achieved following the implementation of debottlenecking initiatives in the prior year, 27 per cent
higher than the previous gold production record.
Integration activity is underway, including the transfer of small volumes of copper concentrate from Prominent Hill to
Olympic Dam for processing. Copper South Australia production of between 310 and 340 kt is expected for the 2024
financial year.
Antamina copper production decreased by eight per cent to 138 kt reflecting the expected lower copper feed grades,
partially offset by higher throughput. Zinc production was one per cent higher at 125 kt, reflecting higher throughput.
Copper production of 120 to 140 kt and zinc production of between 85 and 105 kt is expected for the 2024 financial
year.
Following the acquisition of OZL, Carajás produced 1.6 kt of copper and 1.2 troy koz of gold2.




BHP Operational Review for the year ended 30 June 2023                                                               5
Iron ore
Production
                                                                                         FY23     Jun Q23     Jun Q23
                                                                                           vs          vs          vs
                                                              FY23     Jun Q23           FY22     Jun Q22     Mar Q23
Iron ore (kt)                                               257,043      65,295            1%         2%          9%

Iron ore – Total iron ore production increased by one per cent to 257 Mt. Production for the 2024 financial year is
expected to be between 254 and 264.5 Mt.
WAIO achieved record production of 253 Mt (285 Mt on a 100 per cent basis), reflecting continued strong supply
chain performance, including improved rail performance and increased car dumper utilisation. This was partially offset
by the temporary suspension of operations following the fatality in February, unfavourable weather impacts from
Tropical Cyclone Ilsa in the June 2023 quarter and the ongoing planned tie-in of PDP1, which remains on track to be
completed in the 2024 calendar year.
South Flank remains on track to ramp up to full production capacity of 80 Mtpa (100 per cent basis) by the end of the
2024 financial year. Current year performance has contributed to record annual production at the Mining Area C hub
and record WAIO lump sales. Additionally, the deployment of autonomous haul trucks at South Flank was completed
in May 2023.
WAIO also achieved record shipments for the year, which was inclusive of sales of 249 Mt (281 Mt on a 100 per cent
basis) and inventory in China of almost 4 Mt for portside sales.
WAIO production is expected to increase to between 250 and 260 Mt (282 and 294 Mt on a 100 per cent basis) in the
2024 financial year.
Samarco production increased by 11 per cent to 4.5 Mt (BHP share), as a result of higher concentrator throughput.
Production for the 2024 financial year is expected to be between 4 and 4.5 Mt (BHP share).
In May 2023, Samarco announced it had agreed with its shareholders and a group of Samarco’s financial creditors
to a restructure of the company's financial debts. The agreement was entered into following a 2-month court-
supervised settlement process. The proposed terms are subject to approval by a majority of Samarco’s creditors,
ratification by the Judicial Reorganisation Court and the entry into definitive debt restructure documents. Samarco,
BHP Brasil, Vale, and creditors are working together to implement the restructure terms to resolve Samarco's judicial
reorganisation process.




BHP Operational Review for the year ended 30 June 2023                                                              6
Coal
Production
                                                                                          FY23      Jun Q23     Jun Q23
                                                                                            vs           vs          vs
                                                                 FY23      Jun Q23        FY22      Jun Q22     Mar Q23
Metallurgical coal (kt)                                         29,020       8,477          0%          4%          22%
Energy coal (kt)                                                14,172       4,765          3%         22%          21%

Metallurgical coal – BMA production of 29 Mt (58 Mt on a 100 per cent basis) was in line with the prior period. The
significant wet weather experienced in the first three quarters4 was offset by strong underlying operational
performance, in particular, continued improvement in truck productivity at Goonyella and Daunia following the
completion of their transitions to autonomous fleet. Production for the period was further supported by a drawdown
of raw coal inventory and improved labour availability compared to the prior period.
Production for the 2024 financial year is expected to be between 28 and 31 Mt (56 and 62 Mt on a 100 per cent basis).
The near tripling of top end royalties by the Queensland Government makes Queensland the highest coal taxing regime
in the world. Given the negative impact this has on investment economics and the increase in sovereign risk, we will
not be investing in any further growth in Queensland, however we will sustain and optimise our existing operations.
Energy coal – NSWEC production increased by three per cent to 14.2 Mt driven by an improvement in weather
conditions in the second half of the year and an uplift in truck productivity compared to the prior year. Additional
deployed capacity into a new mining area also resulted in an uplift in prime stripping volumes. Production for the
2024 financial year is expected to be between 13 and 15 Mt.

Higher quality products made up 77 per cent of sales, compared to 89 per cent in the prior period, reflecting the
impacts of the change in export market conditions and the commencement of domestic sales under the NSW
Government Coal Market Price Emergency (Directions for Coal Mines) Notice in the June 2023 quarter. The
reservation allocation for the 2024 financial year is expected to be 0.7 Mt in line with the Directions.


Other
Nickel production
                                                                                          FY23      Jun Q23     Jun Q23
                                                                                            vs           vs          vs
                                                                 FY23      Jun Q23        FY22      Jun Q22     Mar Q23
Nickel (kt)                                                       80.0        22.0          4%         17%          12%

Nickel – Nickel West production increased by four per cent to 80 kt due to an increased proportion of concentrate
and matte products and inventory drawdowns. This was partially offset by the slower than planned ramp up of the
refinery following planned maintenance in the December 2022 quarter and a heavy rain event at the Mt Keith
operations in early April 2023 impacting mine progression.
During the year, Nickel West has experienced ongoing issues with the quality and volume of ore deliveries from
Mincor Resources containing high levels of arsenic, and in March advised that it would no longer accept
off-specification product. In the second half, Nickel West purchased more third-party products compared to the first
half, including higher cost third party concentrate to offset the impact of the ore supply issues.
Production is expected to be between 77 and 87 kt for the 2024 financial year, weighted to the second half of the
year due to planned refinery maintenance in the first half.
The West Musgrave nickel project in Western Australia is in early stages of execution following the final investment
decision by OZL in September 2022 (prior to the acquisition by BHP).
Potash – Our major potash project under development at Jansen is tracking to the accelerated plan with first
production still targeted for the end of the 2026 calendar year, compared to the initial target of the 2027 calendar
year. In the June 2023 quarter, we completed all piling activities for the mill and storage facilities. During the 2024
financial year, we will transition from civil works into steel and equipment installation on the surface and underground,
as well as continuing with equipment procurement. Port construction will also continue. The feasibility study for
Jansen Stage 2 continues to progress and is on track to be completed during the 2024 financial year.

BHP Operational Review for the year ended 30 June 2023                                                                 7
Projects
Project and                         Capital              Initial Capacity                                                       Progress
ownership                       expenditure         production
                                     US$M           target date
Jansen Stage 1                          5,723        End-CY26 Design, engineering and construction of an          Project is 26% complete
(Canada)                                                      underground potash mine and surface
100%                                                          infrastructure, with capacity to produce 4.35 Mtpa.



Minerals exploration
Minerals exploration and evaluation expenditure increased by 37 per cent for the year ended 30 June 2023 to
US$350 million, of which US$294 million was expensed.
At BHP’s recently identified copper porphyry mineralised system, Ocelot, located in the Miami-Globe copper district
of the United States, the final hole of a 6-hole program was completed in May 2023. The project remains at an early
exploration stage and data from the recent drill program will be used to update the overall resource range estimation
at Ocelot.
At Oak Dam in South Australia, we have defined an Exploration Target3 (refer to Appendix 1) and commenced the
next phase of drilling as we work towards defining a first Mineral Resource5. In line with the environmental approvals
received in March 2023, we plan to increase from nine drill rigs to eleven and to establish core processing facilities
and an accommodation camp of up to 150 rooms by the end of the 2023 calendar year. We are continuing community
and stakeholder engagement in preparation for submission of our application to convert the Oak Dam tenement from
an exploration licence to a retention lease, enabling progression of an early access decline.
In addition, we have commenced exploratory drilling beneath the Olympic Dam mine, at depths between 900m and
1,500m, with nine surface exploration rigs.
In June 2023, BHP signed a Sales and Purchase Agreement to acquire 100 per cent of Ragnar Metals Sweden AB,
for a cash payment of A$9.8 million. Ragnar’s assets include the Granmuren Nickel project, an early-stage nickel-
copper tenement package located 110 km north-west of Stockholm, Sweden. BHP intends to undertake additional
drilling to determine whether the known mineralisation has continuous high grade nickel sulphide and to test
additional targets.
The inaugural BHP Xplor accelerator program was completed, with a number of the early-stage mineral exploration
companies selected for further investment. Applications for the program’s second year will open at the end of
August 2023.
Elsewhere, we continue to progress exploration activities in Australia, Canada, Chile, Ecuador, Peru, Serbia and the
United States.


Variance analysis relates to the relative performance of BHP and/or its operations during the 12 months ended June 2023 compared with the 12 months ended June
2022, unless otherwise noted. Production volumes, sales volumes and capital and exploration expenditure from subsidiaries are reported on a 100 per cent basis;
production and sales volumes from equity accounted investments and other operations are reported on a proportionate consolidation basis. Numbers presented may
not add up precisely to the totals provided due to rounding.
The following footnotes apply to this Operational Review:
1 2023 financial year unit cost guidance: Escondida US$1.25-1.45/lb, WAIO US$18-19/t, BMA US$100-105/t and NSWEC US$84-91/t; based on exchange rates
     of AUD/USD 0.72 and USD/CLP 830.
2 Throughout this report, production volumes for the operations acquired from OZL are for the period of 1 May to 30 June 2023, whilst the acquisition completion
     date was 2 May 2023.
3 An Exploration Target is a statement or estimate of the exploration potential of a mineral deposit in a defined geological setting where the statement or estimate,
     quoted as a range of tonnes and a range of grade (or quality), relates to mineralisation for which there has been insufficient exploration to estimate a Mineral
     Resource.
4 803mm of rainfall recorded at Moranbah for the year ended 30 June 2023 compared to 648mm in the prior year.
5 The potential quantity and grade of an Exploration Target is conceptual in nature and as such there has been insufficient exploration to estimate a Mineral
     Resource, and it is uncertain if further exploration or analysis will result in the estimation of a Mineral Resource.

The following abbreviations may have been used throughout this report: cost and freight (CFR); cost, insurance and freight (CIF); dry metric tonne unit (dmtu); free
on board (FOB); grams per tonne (g/t); kilograms per tonne (kg/t); kilometre (km); megawatt (MW); metre (m); millimetre (mm); million tonnes (Mt); million tonnes per
annum (Mtpa); ounces (oz); pounds (lb); thousand ounces (koz); thousand tonnes (kt); thousand tonnes per annum (ktpa); thousand tonnes per day (ktpd); tonnes
(t); and wet metric tonnes (wmt).
In this release, the terms ‘BHP’, the ‘Group’, ‘BHP Group’, ‘we’, ‘us’, ‘our’ and ‘ourselves’ are used to refer to BHP Group Limited and, except where the context
otherwise requires, our subsidiaries. Refer to note 28 ‘Subsidiaries’ of the Financial Statements in BHP’s 30 June 2022 Appendix 4E for a list of our significant
subsidiaries. Those terms do not include non-operated assets. On and from 2 May, the BHP Group includes OZ Minerals Limited and its subsidiaries referred to in
note 17 of their Financial Statements in its Annual Report for the year ended 30 December 2022. Notwithstanding that this release may include production, financial
and other information from non-operated assets, non-operated assets are not included in the BHP Group and, as a result, statements regarding our operations, assets
and values apply only to our operated assets unless stated otherwise. Our non-operated assets include Antamina and Samarco. BHP Group cautions against undue
reliance on any forward-looking statement or guidance in this release, particularly in light of the current economic climate and significant volatility, uncertainty and
disruption arising in connection with COVID-19. These forward-looking statements are based on information available as at the date of this release and are not
guarantees or predictions of future performance and involve known and unknown risks, uncertainties and other factors, many of which are beyond our control and
which may cause actual results to differ materially from those expressed in the statements contained in this release.

BHP Operational Review for the year ended 30 June 2023                                                                                                                8
Further information on BHP can be found at: bhp.com



Authorised for lodgement by:
Stefanie Wilkinson
Group Company Secretary
Sponsor: J.P. Morgan Equities South Africa Proprietary Limited
Media Relations                                          Investor Relations

Email: media.relations@bhp.com                           Email: investor.relations@bhp.com


Australia and Asia                                       Australia and Asia

Gabrielle Notley                                         John-Paul Santamaria
Tel: +61 3 9609 3830 Mobile: +61 411 071 715             Mobile: +61 499 006 018

Europe, Middle East and Africa                           Europe, Middle East and Africa

Neil Burrows                                             James Bell
Tel: +44 20 7802 7484 Mobile: +44 7786 661 683           Tel: +44 20 7802 7144 Mobile: +44 7961 636 432

Americas                                                 Americas

Renata Fernandez                                         Monica Nettleton
Mobile: +56 9 8229 5357                                  Mobile: +1 416 518 6293




BHP Group Limited ABN 49 004 028 077
LEI WZE1WSENV6JSZFK0JC28
Registered in Australia
Registered Office: Level 18, 171 Collins Street
Melbourne Victoria 3000 Australia
Tel +61 1300 55 4757 Fax +61 3 9609 3015




BHP Group is headquartered in Australia
Follow us on social media




BHP Operational Review for the year ended 30 June 2023                                                    9
Production summary

                                                                                Quarter ended                         Year to date
                                                  BHP        Jun       Sep          Dec          Mar       Jun      Jun         Jun
                                                 interest    2022      2022         2022         2023      2023     2023       2022
                                                            Jun-22    Sep-22       Dec-22       Mar-23    Jun-23
Copper1
Copper
Payable metal in concentrate (kt)
  Escondida2                                     57.5%        233.5     203.1         208.3       200.8     220.5     832.7      802.6
  Pampa Norte3                                    100%         28.2      28.6          32.5        32.0      32.2     125.3      111.2
  Copper South Australia4                        100%                                                        19.9      19.9
  Antamina                                       33.8%         39.6      37.1          35.2        29.6      36.5     138.4      149.9
  Carajas5                                       100%                                                         1.6       1.6
  Total                                                       301.3     268.8         276.0       262.4     310.7   1,117.9     1,063.7
Cathode (kt)
  Escondida2                                     57.5%         55.8      49.6          49.7        50.8      72.5     222.6      201.4
  Pampa Norte3                                    100%         49.0      42.0          44.2        41.0      36.3     163.5      170.0
  Copper South Australia4                         100%         55.7      49.7          54.4        51.7      56.7     212.5      138.4
  Total                                                       160.5     141.3         148.3       143.5     165.5     598.6      509.8
Total copper (kt)                                             461.8     410.1         424.3       405.9     476.2   1,716.5     1,573.5
Lead
Payable metal in concentrate (t)
  Antamina                                       33.8%          181       228          114          169       146      657       1,118
  Total                                                         181       228          114          169       146      657       1,118
Zinc
Payable metal in concentrate (t)
  Antamina                                       33.8%       27,576    32,685       29,929       23,612    38,822   125,048    123,200
  Total                                                      27,576    32,685       29,929       23,612    38,822   125,048    123,200
Gold
Payable metal in concentrate (troy oz)
  Escondida2                                     57.5%       45,770    38,236       48,402       48,954    53,503   189,095    166,972
  Pampa Norte3                                    100%        8,198     5,521         3,875       8,152     9,263    26,811     28,870
  Copper South Australia4                         100%                                                     32,736    32,736
  Carajas5                                        100%                                                      1,153     1,153
  Total                                                      53,968    43,757       52,277       57,106    96,655   249,795    195,842
Refined gold (troy oz)
  Copper South Australia4                         100%       26,080    47,184       43,280       49,086    46,479   186,029    119,517
  Total                                                      26,080    47,184       43,280       49,086    46,479   186,029    119,517
Total gold (troy oz)                                         80,048    90,941       95,557      106,192   143,134   435,824    315,359
Silver
Payable metal in concentrate (troy koz)
   Escondida2                                    57.5%        1,311     1,210         1,510       1,346     1,008     5,074      5,334
  Pampa Norte3                                   100%           262       252          245          409       412     1,318      1,011
  Copper South Australia4                        100%                                                         201       201
  Antamina                                       33.8%        1,212     1,190           923         801       971     3,885      5,078
  Total                                                       2,785     2,652         2,678       2,556     2,592    10,478     11,423
Refined silver (troy koz)
  Copper South Australia4                         100%          145       295          261          277       256     1,089          743
  Total                                                         145       295          261          277       256     1,089          743
Total silver (troy koz)                                       2,930     2,947         2,939       2,833     2,848    11,567     12,166
Uranium
Payable metal in concentrate (t)
  Copper South Australia4                         100%          776       817          943          833       813     3,406      2,375
  Total                                                         776       817          943          833       813     3,406      2,375
Molybdenum
Payable metal in concentrate (t)
  Pampa Norte3                                   100%            71        34          216          407       333       990           71
  Antamina                                       33.8%          249       262          348          229       333     1,172          798
  Total                                                         320       296          564          636       666     2,162          869




BHP Operational Review for the year ended 30 June 2023                                                                                     10
Production summary

                                                                                             Quarter ended                             Year to date
                                                        BHP           Jun          Sep           Dec          Mar           Jun      Jun         Jun
                                                      interest       2022          2022          2022         2023          2023     2023       2022

Iron Ore
Iron Ore
Production (kt)6
   Newman                                               85%           14,063        14,053       16,172        11,925       14,795    56,945     57,041
   Area C Joint Venture                                 85%           27,685        26,971       26,302        25,284       28,818   107,375     94,431
   Yandi Joint Venture                                  85%            6,409         5,497        5,613         4,941        5,359    21,410     38,922
   Jimblebar7                                           85%           15,005        17,404       17,720        16,575       15,102    66,801     58,782
   Samarco                                              50%            1,000         1,148        1,095         1,048        1,221     4,512      4,071
   Total                                                              64,162        65,073       66,902        59,773       65,295   257,043    253,247

Coal
Metallurgical coal
Production (kt)8
  BHP Mitsubishi Alliance (BMA)                         50%            8,183         6,662         6,952        6,929        8,477    29,020     29,142
  Total                                                                8,183         6,662         6,952        6,929        8,477    29,020     29,142

Energy coal
Production (kt)
  NSW Energy Coal                                      100%            3,919         2,622         2,851        3,934        4,765    14,172     13,701
  Total                                                                3,919         2,622         2,851        3,934        4,765    14,172     13,701

Other
Nickel
Saleable production (kt)
  Nickel West                                          100%              18.8         20.7          17.7         19.6         22.0      80.0          76.8
  Total                                                                  18.8         20.7          17.7         19.6         22.0      80.0          76.8

Cobalt
Saleable production (t)
  Nickel West                                          100%              110           238              93        175          246      752           632
  Total                                                                  110           238              93        175          246      752           632


  1    Metal production is reported on the basis of payable metal.
  2    Shown on a 100% basis. BHP interest in saleable production is 57.5%.
  3    Includes Spence and Cerro Colorado. Refer to the Production and Sales Report for more details.
  4    Includes Olympic Dam and two months of production from Prominent Hill and Carrapateena from 1 May 2023, following the acquisition of OZL on 2
       May 2023. Refer to the Production and Sales Report for more details.
  5    Includes two months of production from 1 May 2023, following the acquisiton of OZL on 2 May 2023.
  6    Iron ore production is reported on a wet tonnes basis.
  7    Shown on a 100% basis. BHP interest in saleable production is 85%.
  8    Metallurgical coal production is reported on the basis of saleable product. Production figures may include some thermal coal.

  Throughout this report figures in italics indicate that this figure has been adjusted since it was previously reported.




BHP Operational Review for the year ended 30 June 2023                                                                                                      11
Production and sales report

                                                                                         Quarter ended                 Year to date
                                                                   Jun       Sep       Dec         Mar      Jun      Jun         Jun
                                                                   2022      2022      2022       2023      2023     2023       2022


Copper
Metals production is payable metal unless otherwise stated.

Escondida, Chile1
  Material mined                                    (kt)          115,409    110,248   101,987    106,170   95,451   413,856    454,243
  Concentrator throughput                           (kt)           34,318     32,894    33,911     33,309   30,750   130,864    133,868
  Average copper grade - concentrator               (%)             0.88%      0.83%     0.76%      0.78%    0.93%     0.82%      0.78%
  Production ex mill                                (kt)            239.5      214.6     212.8      210.0    228.9     866.3      835.8

  Production
  Payable copper                                    (kt)            233.5     203.1     208.3       200.8    220.5     832.7      802.6
  Copper cathode (EW)                               (kt)             55.8      49.6      49.7        50.8     72.5     222.6      201.4
  - Oxide leach                                     (kt)             17.5      15.2      17.6        14.7     29.3      76.8       57.6
  - Sulphide leach                                  (kt)             38.3      34.4      32.1        36.1     43.2     145.8      143.8
  Total copper                                      (kt)            289.3     252.7     258.0       251.6    293.0   1,055.3    1,004.0
  Payable gold concentrate                          (troy oz)      45,770    38,236    48,402      48,954   53,503   189,095    166,972
  Payable silver concentrate                        (troy koz)      1,311     1,210     1,510       1,346    1,008     5,074      5,334

  Sales
  Payable copper                                    (kt)            230.4     196.7     216.0       197.3    220.3     830.3      798.1
  Copper cathode (EW)                               (kt)             58.9      45.9      53.5        43.8     78.0     221.2      202.5
  Payable gold concentrate                          (troy oz)      45,770    38,236    48,402      48,954   53,503   189,095    166,972
  Payable silver concentrate                        (troy koz)      1,311     1,210     1,510       1,346    1,008     5,074      5,334

  1   Shown on a 100% basis. BHP interest in saleable production is 57.5%.

Pampa Norte, Chile
  Cerro Colorado
  Material mined                                    (kt)            3,604     3,179       583         172      145     4,079     17,280
  Ore stacked                                       (kt)            4,259     4,373     4,119       3,567    3,928    15,987     15,035
  Average copper grade - stacked                    (%)             0.55%     0.54%     0.56%       0.57%    0.53%     0.55%      0.58%

  Production
  Copper cathode (EW)                               (kt)              14.7     12.8       12.2       12.0     12.2      49.2          55.0

  Sales
  Copper cathode (EW)                               (kt)              16.2     13.3       12.2       10.9     14.1      50.5          54.8

  Spence
  Material mined                                    (kt)           26,749    26,956    26,980      24,858   25,622   104,416     95,968
  Ore stacked                                       (kt)            5,099     5,577     5,155       4,947    5,625    21,304     20,483
  Average copper grade - stacked                    (%)             0.66%     0.70%     0.66%       0.60%    0.58%     0.64%      0.66%
  Concentrator throughput                           (kt)            6,311     6,433     7,602       7,290    6,927    28,252     24,843
  Average copper grade - concentrator               (%)             0.66%     0.63%     0.60%       0.61%    0.61%     0.61%      0.64%

  Production
  Payable copper                                    (kt)             28.2      28.6      32.5        32.0     32.2     125.3      111.2
  Copper cathode (EW)                               (kt)             34.3      29.2      32.0        29.0     24.1     114.3      115.0
  Total copper                                      (kt)             62.5      57.8      64.5        61.0     56.3     239.6      226.2
  Payable gold concentrate                          (troy oz)       8,198     5,521     3,875       8,152    9,263    26,811     28,870
  Payable silver concentrate                        (troy koz)        262       252       245         409      412     1,318      1,011
  Payable molybdenum                                (t)                71        34       216         407      333       990         71

  Sales
  Payable copper                                    (kt)             28.1      26.0      22.0        38.7     38.6     125.3      109.5
  Copper cathode (EW)                               (kt)             35.4      29.1      33.4        25.1     28.3     115.9      114.5
  Payable gold concentrate                          (troy oz)       8,198     5,521     3,875       8,152    9,263    26,811     28,870
  Payable silver concentrate                        (troy koz)        262       252       245         409      412     1,318      1,011
  Payable molybdenum                                (t)                25        25       216         492      367     1,100         25




BHP Operational Review for the year ended 30 June 2023                                                                                       12
Production and sales report

                                                                                              Quarter ended                    Year to date
                                                                    Jun         Sep         Dec          Mar        Jun      Jun         Jun
                                                                   2022        2022         2022        2023        2023     2023       2022


Copper (continued)
Metals production is payable metal unless otherwise stated.

Copper South Australia
  Olympic Dam
  Material mined1                                   (kt)             2,477       2,412        2,264       2,317      2,356     9,349      8,834
  Ore milled                                        (kt)             2,436       2,570        2,687       2,433      2,755    10,445      7,687
  Average copper grade                              (%)              2.15%       2.13%        2.08%       1.95%      2.00%     2.04%      2.14%
  Average uranium grade                             (kg/t)            0.56        0.58         0.58        0.59       0.55      0.58        0.57


  Production
  Copper cathode (ER and EW)                        (kt)              55.7        49.7         54.4        51.7       56.7     212.5      138.4
  Payable uranium                                   (t)                776         817          943         833        813     3,406      2,375
  Refined gold                                      (troy oz)       26,080      47,184       43,280      49,086     46,479   186,029    119,517
  Refined silver                                    (troy koz)         145         295          261         277        256     1,089        743

  Sales
  Copper cathode (ER and EW)                        (kt)              55.8        45.9         56.8        50.5       59.5     212.7      139.1
  Payable uranium                                   (t)              1,031         272        1,127         683      1,275     3,357      2,344
  Refined gold                                      (troy oz)       24,622      49,542       41,900      47,300     49,182   187,924    118,979
  Refined silver                                    (troy koz)          87         320          233         307        270     1,130        685

  Prominent Hill2
  Material mined                                    (kt)                                                               661       661
  Ore milled                                        (kt)                                                             1,228     1,228
  Average copper grade                              (%)                                                              0.77%     0.77%
  Production ex mill                                (kt)                                                              16.3      16.3

  Production
  Payable copper                                    (kt)                                                               8.2       8.2
  Payable gold concentrate                          (troy oz)                                                       17,432    17,432
  Payable silver concentrate                        (troy koz)                                                          44        44

  Sales
  Payable copper                                    (kt)                                                              15.7      15.7
  Payable gold concentrate                          (troy oz)                                                       28,856    28,856
  Payable silver concentrate                        (troy koz)                                                          87        87

  Carrapateena2
  Material mined                                    (kt)                                                               880       880
  Ore milled                                        (kt)                                                               856       856
  Average copper grade                              (%)                                                              1.52%     1.52%
  Production ex mill                                (kt)                                                              30.1      30.1

  Production
  Payable copper                                    (kt)                                                              11.7      11.7
  Payable gold concentrate                          (troy oz)                                                       15,304    15,304
  Payable silver concentrate                        (troy koz)                                                         157       157

  Sales
  Payable copper                                    (kt)                                                              11.9      11.9
  Payable gold concentrate                          (troy oz)                                                       15,242    15,242
  Payable silver concentrate                        (troy koz)                                                         155       155

  1   Material mined refers to underground ore mined, subsequently hoisted or trucked to surface.
  2   Includes two months of production and sales from 1 May 2023, following the acquisiton of OZL on 2 May 2023.




BHP Operational Review for the year ended 30 June 2023                                                                                            13
Production and sales report

                                                                                              Quarter ended                       Year to date
                                                                    Jun         Sep         Dec          Mar        Jun         Jun         Jun
                                                                   2022        2022         2022        2023        2023        2023       2022


Copper (continued)
Metals production is payable metal unless otherwise stated.

Antamina, Peru
  Material mined (100%)                             (kt)            64,026      63,865       68,750      57,939     62,894      253,448    246,904
  Concentrator throughput (100%)                    (kt)            13,131      13,858       14,272      12,349     13,897       54,376     52,496
  Average head grades
  - Copper                                          (%)              1.02%       0.93%        0.86%       0.88%      0.88%        0.89%      0.98%
  - Zinc                                            (%)              1.05%       1.09%        0.99%       1.06%      1.25%        1.10%      1.11%

  Production
  Payable copper                                    (kt)              39.6        37.1         35.2        29.6       36.5        138.4      149.9
  Payable zinc                                      (t)             27,576      32,685       29,929      23,612     38,822      125,048    123,200
  Payable silver                                    (troy koz)       1,212       1,190          923         801        971        3,885      5,078
  Payable lead                                      (t)                181         228          114         169        146          657      1,118
  Payable molybdenum                                (t)                249         262          348         229        333        1,172        798

  Sales
  Payable copper                                    (kt)              40.7        37.6         34.7        32.4       34.5        13 ...