LNG DELIVERIES COMMENCE AND HELIUM OPERATIONAL UPDATE


Renergen would like to inform investors that following the maintenance outage, LNG deliveries
have re-commenced.

The delays suffered during the planned maintenance outage were primarily as a result of the
scheduled maintenance period being brought forward to coincide with the helium coldbox
repair. The shut down ran longer than expected owing to unexpected challenges experienced
with the primary mixed refrigerant compressors. These compressors were supplied by a
company which is part of a global Swiss compressor manufacturing group, which includes
China where the compressors were assembled. The Original Equipment Manufacturer
(“OEM”), Local agent and Swiss Head-office together with our project and engineering teams
were able to diagnose the problem and determine the root cause. As a result of the losses
suffered due to the delay, the Company will seek to obtain relief from insurance cover and or
a contractual claim against its suppliers.

We have turned our full attention to the helium system following the successful repair and
testing of the helium cold box last year. We are currently awaiting the arrival of the OEM which
will occur following the Chinese New Year celebrations. Once in the country they will finalise
the integration of the helium system into the overall plant and then undertake a final
performance test to ensure the entire plant performs according to its original design
specifications.

In preparation, the nitrogen and helium systems will be filled with externally sourced
refrigerant, primarily pure gaseous nitrogen and helium, which are essential to the cooling
process of the respective coldboxes.


Johannesburg
15 February 2024
Authorised by: Stefano Marani
Chief Executive Officer

Designated Advisor
PSG Capital

www.renergen.co.za

For all media relations please contact:
Mandy Stuart
Head of Marketing & ESG Management
mandy@renergen.co.za

For all US investors and media relations please contact:
Georg Venturatos / Jared Gornay – Gateway Group, (949) 574-3860
Ren@gateway-grp.com