Try our mobile app

Quarterly Activities Report

Published: 2022-07-19 11:33:02 ET
<<<  go to JSE:BHG company page
 BHP Group Limited
 BHP Group Limited
 ABN 49 004 028 077
 Registered in Australia
 Registered Office: Level 18, 171
 Collins Street Melbourne VIC 3000
 Share code: BHG
 ISIN: AU000000BHP4




Release Time                   IMMEDIATE
Date                           19 July 2022
Release Number                 24/22
BHP OPERATIONAL REVIEW
FOR THE YEAR ENDED 30 JUNE 2022
Note: All guidance is subject to further potential impacts from COVID-19 during the 2023 financial year.

 We continue to deliver safe and reliable production. We remained fatality free during the year and have
  delivered record sales volumes from Western Australia Iron Ore (WAIO), allowing us to fully capitalise
  on the opportunity presented by high iron ore prices.

 Full year production guidance for iron ore and energy coal were achieved, as were revised guidance for
  copper and metallurgical coal. Full year nickel production was lower than revised guidance due to a
  smelter outage in the June 2022 quarter.

 Full year unit cost guidance1 is expected to be achieved for WAIO and Escondida. New South Wales
  Energy Coal (NSWEC) unit costs are expected to be towards the bottom end of revised guidance, which
  was updated to reflect a targeted increase in the proportion of higher quality energy coal to capture
  more value from record high prices. BMA unit costs are expected to be marginally above revised
  guidance for Queensland Coal primarily due to the impact of the divestment of BMC.

 The Jansen shaft project was completed in the June 2022 quarter. Jansen Stage 1 is tracking to plan,
  with activities progressing at the port and at the Jansen site. We are working to bring forward Jansen
  Stage 1 first production into 2026 and are assessing options to accelerate Jansen Stage 2.
 The divestment of BHP’s 80% interest in BMC to Stanmore and the merger of BHP’s oil and gas portfolio
  with Woodside Energy were completed during the June 2022 quarter.
 BHP announced that it will retain NSWEC in its portfolio and seek relevant approvals to enable mining
  beyond the current mining consent that expires in 2026, towards a cessation of mining in 2030.
 The financial results for the second half of the 2022 financial year are expected to reflect certain items
  as summarised in the table on page 3.


Production                            FY22         Jun Q22 Jun Q22 vs Mar Q22 commentary
                               (vs FY21)       (vs Mar Q22)
Copper (kt)                          1,573.5         461.8 Higher volumes at Escondida due to increased grade and concentrator throughput,
                                        (4%)          25% at Spence due to improved leaching performance and at Olympic Dam following major
                                                           smelter maintenance campaign impacts in the prior period.
Iron ore (Mt)                         253.2            64.2 Higher volumes at WAIO reflecting record production from the Mining Area C hub with
                                        0%              8% the continued ramp up of South Flank and improved supply chain performance.
Metallurgical coal (Mt)2                29.1            8.2 Higher volumes driven by improved truck productivity, partially offset by heavy rainfall
                                       (9%)             3% in the quarter.
Energy coal (Mt)3                       13.7           3.9 Higher volumes due to less wet weather and reduced COVID-19 related labour
                                       (4%)           52% impacts.
Nickel (kt)                             76.8           18.8 Higher volumes due to reduced COVID-19 labour impacts, offset by an unplanned
                                      (14%)             1% smelter outage.

Group copper equivalent production for the 2022 financial year decreased by 4%4 mainly due to lower copper and coal volumes.
Group copper equivalent production for the 2023 financial year is expected to increase by approximately 4% from the
2022 financial year.




BHP Operational Review for the year ended 30 June 2022                                                                                                 1
Summary

BHP Chief Executive Officer, Mike Henry:
“BHP produced a strong fourth quarter to cap off a year of significant progress. Our performance for the year has been
underpinned by safe, reliable operations and firm demand for our commodities. We completed another year fatality free
and we are unwavering in our effort to improve safety, and this includes addressing sexual assault and harassment,
racism and bullying.
We delivered record full-year sales volumes at our iron ore business in Western Australia as a result of reliable
operational performance and the South Flank project which continued to ramp up. In copper, Escondida in Chile had
record material mined and near-record concentrator throughput, while Olympic Dam in South Australia performed
strongly in the fourth quarter after planned smelter maintenance.

Queensland metallurgical coal delivered strong underlying performance for the quarter in the face of significant wet
weather. BHP is assessing the impacts on BMA economic reserves and mine lives as a result of the increase in coal
royalties by the Queensland Government. The near tripling of top end royalties has worsened what was already one of
the world’s highest coal royalty regimes, threatening investment and jobs in the state.
Our US$5.7 billion Jansen potash project in Canada is tracking to plan and we are working to bring first production
forward to 2026. Also during the year, we merged our petroleum business with Woodside, completed the sales of BMC
and Cerrejón, and decided to retain New South Wales Energy Coal until the cessation of mining in 2030 subject to
relevant approvals. We also unified our corporate structure, and added to our global options in copper and nickel.

Broader market volatility continues and we expect the lag effect of inflationary pressures to continue through the
2023 financial year, along with labour market tightness and supply chain constraints. Over the year ahead, China is
expected to contribute positively to growth as stimulus policies take effect, however, the continuing conflict in the
Ukraine, the unfolding energy crisis in Europe and policy tightening globally is expected to result in an overall slowing
of global growth. Our strong focus on safety, operational reliability, cost control and social value will help us navigate
these challenges and continue to deliver for all of our stakeholders.”

Operational performance

Production and guidance are summarised below.

Note: All guidance is subject to further potential impacts from COVID-19 during the 2023 financial year.
                                                                         FY22      Jun Q22      Jun Q22
                                                                 Jun       vs           vs           vs             FY23           FY23e
Productioni                                           FY22       Q22     FY21      Jun Q21      Mar Q22         guidance         vs FY22
Copper (kt)                                         1,573.5    461.8      (4%)         15%          25%     1,635 – 1,825      4% – 16%
    Escondida (kt)                                  1,004.0    289.3      (6%)         17%          28%     1,080 – 1,180      8% – 18%
    Pampa Norte (kt)                                  281.2     77.2      29%          11%          13%         240 – 290     (15%) – 3%
    Olympic Dam (kt)                                  138.4     55.7    (33%)          10%          43%         195 – 215     41% – 55%
    Antamina (kt)                                     149.9     39.6       4%          10%          10%         120 – 140   (20%) – (7%)
Iron ore (Mt)                                         253.2     64.2       0%          (2%)          8%         249 – 260      (2%) – 3%
    WAIO (Mt)                                         249.2     63.2      (1%)         (2%)          8%         246 – 256      (1%) – 3%
    WAIO (100% basis) (Mt)                            282.8     71.7       0%          (2%)          7%         278 – 290      (2%) – 3%
    Samarco (Mt)                                        4.1       1.0    110%          (2%)          1%              3–4    (26%) – (2%)
Metallurgical coal - BMA (Mt)                          29.1       8.2     (9%)        (12%)          3%           29 – 32      0% – 10%
    Metallurgical coal - BMA (100% basis) (Mt)         58.3     16.4      (9%)        (12%)          3%           58 – 64      0% – 10%
Energy coal – NSWEC (Mt)                               13.7       3.9     (4%)        (13%)         52%           13 – 15      (5%) – 9%
Nickel (kt)                                            76.8     18.8    (14%)         (16%)          1%           80 – 90      4% – 17%
i      Excludes BMC and Petroleum production. The divestment of BHP's 80 per cent interest in BMC to Stanmore Resources Limited and the
       merger of BHP's oil and gas portfolio with Woodside Energy Group Limited were completed on 3 May 2022 and 1 June 2022 respectively.
       Production data for these assets are below in the production and sales report.




BHP Operational Review for the year ended 30 June 2022                                                                                  2
Summary of disclosures

BHP expects its financial results for the second half of the 2022 financial year to reflect certain items as summarised
in the table below. The table does not provide a comprehensive list of all items impacting the period. The financial
statements are the subject of ongoing work that will not be finalised until the release of BHP’s financial results on
16 August 2022. Accordingly the information in the table below contains preliminary information that is subject to update
and finalisation.
                                                                                                       H2 FY22
                                                                                                        impact
Description                                                                                              US$Mi                   Classificationii
Unit costs for WAIO, Escondida and NSWEC are expected to be in line with full year                             -                 Operating costs
guidance (at guidance exchange rates), with NSWEC tracking towards the bottom end of
revised guidance
Note: weaker Australian dollar and Chilean peso than guidance rates in the periodiii
Unit costs for BMA are expected to be marginally above full year revised guidance for                          -               ↑ Operating costs
Queensland Coal, due to the impact of the divestment of BMC, and higher diesel and
electricity prices (at guidance exchange rates)
Note: weaker Australian dollar than guidance rates in the periodiii
Impairment charge related to an increase in closure and rehabilitation provision at Cerro             400 – 450                ↑ Operating costs
Colorado due to additional work required to re-profile waste dumps for closure and an
increase in scope for the closure activities
Exploration expense (minerals exploration programs)                                                         119             Exploration expense
The Group’s adjusted effective tax rate for the full year is expected to be within the guidance                -               Taxation expense
range of 30 to 35 per cent
Dividends paid to non-controlling interests                                                        1,250 – 1,300        ↑ Financing cash outflow
Gain on sale of BHP’s 80 per cent interest in BMC (after tax)                                         825 – 875          ↑ Exceptional item gain
Net proceeds received from the sale of BHP’s 80 per cent interest in BMC
              iv
                                                                                                         ~1,250           ↑ Investing cash inflow
Transaction costs related to Unification (after tax)                                                       ~430       ↑ Exceptional item charge
                                                                                                               v
Financial impact on BHP Brasil of the Samarco dam failure                                         Refer footnote                Exceptional item
Discontinued operations
Gain on merger of BHP’s oil and gas portfolio (after tax)                                          8,000 – 8,300         ↑ Exceptional item gain
Net cash payment to Woodside at completion of the merger and cash left in the BHP                        ~1,100         ↑ Investing cash outflow
Petroleum bank accounts to fund ongoing operationsvi
i     Numbers are not tax effected, unless otherwise noted.
ii    There will be a corresponding balance sheet, cash flow and/or income statement impact as relevant, unless otherwise noted.
iii   Average exchange rates for FY22 of AUD/USD 0.73 (guidance rate AUD/USD 0.78) and USD/CLP 811 (guidance rate USD/CLP 727).
iv    Net of cash remaining in BMC on completion of US$63 million.
v     Financial impact is the subject of ongoing work and is not yet finalised. See corporate update section for further information on Samarco.
vi    As part of completion, BHP made a net cash payment of US$0.7 billion to Woodside. The net payment to Woodside is subject to a customary
      post-completion review which may result in an adjustment to the amount paid. In addition, US$0.4 billion in cash was left in the BHP
      Petroleum bank accounts.

Major development projects

In June 2022, we completed the US$2.97 billion Jansen mine shafts project.

At the end of the 2022 financial year, BHP had one major project under development, the US$5.7 billion Jansen
Stage 1 project, which is tracking to plan.




BHP Operational Review for the year ended 30 June 2022                                                                                             3
Average realised prices

The average realised prices achieved for our major commodities are summarised below.
                                                                                                             FY22       Jun H22       Jun H22
                                                                                                               vs            vs            vs
Average realised pricesi                       Jun H22        Dec H21           FY22          FY21           FY21       Jun H21       Dec H21
Copper (US$/lb)                                     4.02          4.31           4.16          3.81            9%           (7%)          (7%)
Iron ore (US$/wmt, FOB)                          112.65         113.54        113.10         130.56         (13%)         (29%)           (1%)
Metallurgical coal (US$/t)                       423.82         259.71        347.10         106.64         225%           269%           63%
    Hard coking coal (US$/t)ii                   437.60         278.60        366.82         112.72         225%           269%           57%
                                 ii
    Weak coking coal (US$/t)                     382.56         218.65        296.51          89.62         231%           266%           75%
                     iii
Thermal coal (US$/t)                             302.60         137.68        216.78          58.42         271%           327%          120%
 Nickel metal (US$/t)                                27,399      19,651         23,275       16,250           43%           56%            39%
i     Based on provisional, unaudited estimates. Prices exclude sales from equity accounted investments, third party product and internal sales,
      and represent the weighted average of various sales terms (for example: FOB, CIF and CFR), unless otherwise noted. Includes the impact
      of provisional pricing and finalisation adjustments.
ii    Hard coking coal (HCC) refers generally to those metallurgical coals with a Coke Strength after Reaction (CSR) of 35 and above, which
      includes coals across the spectrum from Premium Coking to Semi Hard Coking coals, while weak coking coal (WCC) refers generally to
      those metallurgical coals with a CSR below 35.
iii   Includes thermal coal sales from metallurgical coal mines.

The large majority of iron ore shipments were linked to index pricing for the month of shipment, with price differentials
predominantly a reflection of market fundamentals and product quality. Iron ore sales for the June 2022 half year
were based on an average moisture rate of 6.9 per cent. The large majority of metallurgical coal and energy coal
exports were linked to index pricing for the month of scheduled shipment or priced on the spot market at fixed or
index-linked prices, with price differentials reflecting product quality. The majority of copper cathodes sales were
linked to index price for quotation periods one month after month of shipment, and three to four months after month
of shipment for copper concentrates sales with price differentials applied for location and treatment costs.

At 30 June 2022, the Group had 354 kt of outstanding copper sales that were revalued at a weighted average price
of US$3.75 per pound. The final price of these sales will be determined in the 2023 financial year. In addition, 323 kt
of copper sales from the 2021 financial year were subject to a finalisation adjustment in the current financial year.
The provisional pricing and finalisation adjustments will decrease Underlying EBITDA by US$473 million in the
2022 financial year and are included in the average realised copper price in the above table.

Corporate update

Portfolio

In April 2022, we signed a letter of intent with a consortium led by the Global Maritime forum to assess the
development of an iron ore Green Corridor between Australia and East Asia. Green Corridors are specific shipping
routes where the economics, infrastructure and logistics of zero or near-zero emission shipping are more feasible
and where deployment can be supported by targeted policy and industry action. The new consortium will facilitate a
robust public-private dialogue to investigate conditions that need to be in place to mobilise demand and to feasibly
scale zero or near-zero- greenhouse gas emission shipping on the corridor.

On 3 May 2022, BHP completed the sale of its 80 per cent interest in BMC to Stanmore Resources Limited. Stanmore
Resources paid US$1.1 billion cash consideration at completion plus a preliminary completion adjustment of
approximately US$200 million for working capital. US$100 million cash remains payable to BHP on 3 November
2022 with potential for an additional amount of up to US$150 million in a price-linked earnout payable to BHP in the
2024 calendar year. The total cash consideration for the transaction could be up to US$1.35 billion plus the final
completion adjustment amount. The Group expects to recognise a net gain on sale of between US$825 million and
US$875 million post-tax as an exceptional item in the 2022 financial year.

On 1 June 2022, the merger of BHP’s oil and gas portfolio with Woodside was completed. BHP paid a fully franked
in specie dividend and distributed Woodside shares to eligible BHP shareholders. The implied value of the in specie
dividend was approximately US$19.6 billion or US$3.86 per BHP share. The sale of the Woodside shares of ineligible
overseas shareholders and BHP shareholders that elected to participate in the sale facility, was completed and the
proceeds have been distributed to participating shareholders. As part of completion, BHP made a net cash payment
of approximately US$0.7 billion to Woodside. The net payment to Woodside is subject to a customary post-
BHP Operational Review for the year ended 30 June 2022                                                                                        4
completion review which may result in an adjustment to the amount paid. The Group expects to recognise a net gain
on the merger of between US$8.0 billion and US$8.3 billion post-tax as an exceptional item in the 2022 financial
year5.

On 16 June 2022, BHP announced that we will retain New South Wales Energy Coal (NSWEC) in our portfolio, seek
the relevant approvals to continue mining beyond its current mining consent that expires in 2026 and proceed with a
managed process to cease mining at the asset by the end of the 2030 financial year. A trade sale process for NSWEC
was conducted however the process did not result in a viable offer. Assessment of the resource economics,
geotechnical profile and future investment requirements determined that continued mining in the near term and
moving to closure in 2030 provides the optimal financial outcome when compared to alternate options. Continuation
of mining to the end of the 2030 financial year will afford eight years to work with our people, state and federal
governments and local communities in the Hunter Valley region on a transition approach that supports long-term
community sustainability.

Samarco

Samarco’s Judicial Reorganisation process is continuing in the Commercial Courts of Belo Horizonte, State of Minas
Gerais. The Judicial Reorganisation is a process for Samarco to restructure its financial debts in order to establish a
sustainable independent financial position that would allow Samarco to, among other things, continue its operations
safely and meet its Renova Foundation obligations. BHP Brasil will continue to support Samarco in this process. The
Judicial Reorganisation is not expected to affect Samarco’s obligation or commitment to make full redress for the
2015 Fundão dam failure, and it does not impact Renova Foundation’s ability to undertake remediation and
compensation works.

Separately, negotiations are also ongoing with State and Federal Prosecutors and other Brazilian public authorities
on the review of the Framework Agreement6, seeking a definitive and substantive settlement of Brazilian claims
relating to the dam failure.

On 8 July 2022, the United Kingdom (UK) Court of Appeal decided to allow the group action in the UK against BHP
seeking compensation on behalf of individuals, municipalities, private businesses and indigenous peoples in Brazil
to continue in the UK. The judgment overturns the earlier decision of the High Court that dismissed the group action.
BHP has sought permission to appeal the judgment to the UK Supreme Court. The judgment is not a decision in
relation to the merits of the claims made in the group action. It is concerned with the preliminary question of whether
the group action can continue against BHP in the United Kingdom.

The impact of this decision and recent legal decisions in Brazil on the Group’s Samarco provision is currently being
assessed.

We will provide an update to the ongoing potential financial impacts on BHP Brasil of the Samarco dam failure with
the release of the financial results on 16 August 2022. Any financial impacts will continue to be treated as an
exceptional item.




BHP Operational Review for the year ended 30 June 2022                                                               5
Copper

Production
                                                                                        FY22     Jun Q22      Jun Q22
                                                                                          vs          vs           vs
                                                               FY22      Jun Q22        FY21     Jun Q21      Mar Q22
Copper (kt)                                                   1,573.5      461.8        (4%)         15%         25%
Zinc (t)                                                     123,200      27,576       (15%)        (22%)       (16%)
Uranium (t)                                                    2,375         776       (27%)         26%         (1%)

Copper – Total copper production decreased by four per cent to 1,574 kt. Production for the 2023 financial year is
expected to be between 1,635 and 1,825 kt.
Escondida copper production decreased by six per cent to 1,004 kt primarily due to higher than expected concentrator
feed grade decline of four per cent, public road blockades affecting access to site for both workers and supplies, and
the impact of a reduced operational workforce from COVID-19. Despite these challenges, Escondida achieved record
material mined for the 2022 financial year and near record concentrator throughput of 367 ktpd. Production is
expected to increase to between 1,080 and 1,180 kt for the 2023 financial year and reflects an expected increase in
concentrator feed grade compared to the 2022 financial year. Medium term guidance of 1.2 Mtpa of copper production
on average over the next five years remains unchanged, with production expected to be weighted towards the latter
years.

Pampa Norte copper production increased by 29 per cent to 281 kt reflecting the ramp up of the Spence Growth
Option (SGO), partially offset by the impact of lower cathode production as a result of a 14 per cent decline in Pampa
Norte stacking feed grade. Production for the 2023 financial year is expected to be between 240 and 290 kt. This
reflects a forecast decline in stacking feed grade at Pampa Norte, the commencement of plant design modifications
at SGO and the continued transition towards the planned closure of Cerro Colorado at the end of the 2023 calendar
year.

Olympic Dam copper production decreased by 33 per cent to 138 kt as a result of the major smelter maintenance
campaign (SCM21), which included COVID-19 impacts on the availability of workforce and was subsequently
completed in January 2022. Near record production in the June 2022 quarter followed the successful ramp up of the
smelter to full capacity in April 2022. Average copper grade of 2.14 per cent was achieved in the 2022 financial year
as the majority of material mined is from the Southern Mine Area. Production for the 2023 financial year is expected
to increase to between 195 and 215 kt.

Antamina copper production increased by four per cent to 150 kt, reflecting higher copper head grades. Zinc
production decreased by 15 per cent to 123 kt reflecting lower zinc head grades. Copper production of between
120 and 140 kt, and zinc production of between 115 and 135 kt is expected for the 2023 financial year.




BHP Operational Review for the year ended 30 June 2022                                                              6
Iron Ore

Production
                                                                                         FY22      Jun Q22     Jun Q22
                                                                                           vs           vs          vs
                                                                FY22      Jun Q22        FY21      Jun Q21     Mar Q22
Iron ore production (kt)                                      253,247       64,162         0%         (2%)          8%

Iron ore – Total iron ore production was in line with the prior period at 253 Mt. Production for the 2023 financial year
is expected to be between 249 and 260 Mt.
WAIO production of 249 Mt (283 Mt on a 100 per cent basis) was in line with the prior period, reflecting continued
strong supply chain performance and favourable weather compared to the prior period, offset by the impacts of
temporary labour constraints relating to COVID-19, planned track renewal works in the March 2022 quarter and the
planned major maintenance on the Jimblebar train load out and car dumper one in the first half. Our preventative
maintenance programs continue to underpin the strength of the WAIO supply chain, delivering increased car dumper,
reclaimer and ship loader availability year on year and enabling record sales volumes of 284 Mt (100 per cent basis).
South Flank ramp up to full production capacity of 80 Mtpa (100 per cent basis) is ahead of schedule with an average
rate of 67 Mtpa achieved in the June 2022 quarter contributing to record production from the Mining Area C (MAC)
hub and record lump sales.
WAIO production for the 2023 financial year is expected to be between 246 and 256 Mt (278 and 290 Mt on a 100 per
cent basis) reflecting the tie-in of the port debottlenecking project (PDP1) and the continued ramp up of South Flank.

Samarco production of 4.1 Mt (BHP share) reflected the ramp up of production to capacity, following the
recommencement of iron ore pellet production at one concentrator in December 2020. Production for the
2023 financial year is expected to be between 3 and 4 Mt (BHP share).



Coal

Production
                                                                                         FY22      Jun Q22     Jun Q22
                                                                                           vs           vs          vs
                                                                FY22      Jun Q22        FY21      Jun Q21     Mar Q22
                          2
Metallurgical coal (kt)                                       29,142        8,183         (9%)       (12%)          3%
                   3
Energy coal (kt)                                              13,701        3,919         (4%)       (13%)         52%

Metallurgical coal – BMA production decreased by nine per cent to 29 Mt (58 Mt on a 100 per cent basis). Significant
wet weather impacts across most BMA operations and labour constraints, including COVID-19 related absenteeism
which impacted stripping and mine productivity, more than offset record production at the Broadmeadow mine.
Following the automation of Daunia’s truck fleet in November 2021, the automation of Goonyella’s pre-strip truck
fleet was completed in March 2022 with the Goonyella coal truck fleet expected to be fully autonomous by the end
of the December 2022 quarter. Production for the 2023 financial year is expected to be between 29 and 32 Mt (58 and
64 Mt on a 100 per cent basis). A long wall move at Broadmeadow mine is scheduled for the September 2022 quarter.
The divestment of our interest in BMC was completed on 3 May 2022 and BMC volumes are no longer included in
metallurgical coal volumes.
Following the announcement of the change to the Queensland royalty regime from 1 July 2022, we will assess the
impact on production, jobs and the communities of Central Queensland. At spot metallurgical coal prices7, the
effective pre-tax royalty rate has increased by approximately 7 percentage points to 19 per cent. This further cost
pressure will discourage investment, operational growth, job creation and local business spending across the state.
The new tax damages Queensland’s reputation as a stable place to invest, and will make it harder for the state to
compete against other global jurisdictions in attracting major new investments that would deliver longer term value
to communities and the state economy.



BHP Operational Review for the year ended 30 June 2022                                                                7
Energy coal – NSWEC production decreased by four per cent to 14 Mt, reflecting lower volumes due to an increased
proportion of washed coal to capitalise on higher margins for higher quality coals, COVID-19 related labour
constraints which impacted stripping performance and mine productivity, and wet weather. Higher quality coals now
make up almost 90 per cent of sales compared to approximately 60 per cent of sales in the prior year. Production for
the 2023 financial year is expected to be between 13 and 15 Mt reflecting a continued focus on higher quality coals.



Other

Nickel production
                                                                                                       FY22        Jun Q22       Jun Q22
                                                                                                         vs             vs            vs
                                                                         FY22        Jun Q22           FY21        Jun Q21       Mar Q22
Nickel (kt)                                                               76.8           18.8          (14%)          (16%)              1%

Nickel – Nickel West production decreased by 14 per cent to 77 kt due to the significant impacts of COVID-19 related
labour absenteeism and workforce shortages, and unplanned downtime at the oxygen plant leading to a 15 day
smelter outage in the June 2022 quarter. Production for the 2023 financial year is expected to be between 80 and
90 kt, weighted to the second half of the year due to planned smelter maintenance in the first half.
Potash – Our major potash project under development is tracking to plan.

Projects
Project and                  Capital          Initial Capacity                                             Progress
ownership                expenditure     production
                              US$M       target date
Jansen Potash                   2,972          CY27 Investment to finish the excavation and lining of      100% complete. This project
(Canada)                                            the production and service shafts, and to continue     will not be reported in the
100%                                                the installation of essential surface infrastructure   projects section of future
                                                    and utilities.                                         Operational Reviews.
Jansen Stage 1                  5,723          CY27 Design, engineering and construction of an          Approved in August 2021,
(Canada)                                            underground potash mine and surface                 project is 8% complete
100%                                                infrastructure, with capacity to produce 4.35 Mtpa.




Minerals exploration
Total minerals exploration expenditure for 2022 financial year was US$256 million, of which US$199 million was
expensed.

Work continues on existing exploration projects, joint ventures and farm-in agreements, as well as leveraging
technology to both look deeper in mature exploration jurisdictions and delineate new high potential search spaces
globally. Greenfield minerals exploration is being undertaken on advancing copper targets in Chile, Ecuador, Mexico,
Peru, Canada, Australia and the south-west United States. Nickel targets are also being advanced in Canada and
Australia.

We continued to progress our early stage options in future facing commodities throughout the year. Work continued
on the farm-in agreement executed in October 2021 for the early-stage Elliott copper project covering 7,200 km 2 in
the Northern Territory, Australia, and in April 2022 we agreed to fund a nickel exploration program in Nunavik,
Quebec, as part of our strategic alliance with Midland Exploration8.

At Oak Dam in South Australia, BHP is continuing next stage resource definition drilling with six drill rigs.




BHP Operational Review for the year ended 30 June 2022                                                                                    8
Variance analysis relates to the relative performance of BHP and/or its operations during the 2022 financial year compared with the 2021 financial year, unless
otherwise noted. Production volumes, sales volumes and capital and exploration expenditure from subsidiaries are reported on a 100 per cent basis; production and
sales volumes from equity accounted investments and other operations are reported on a proportionate consolidation basis. Numbers presented may not add up
precisely to the totals provided due to rounding. Copper equivalent production is based on 2022 financial year average realised prices.

The following footnotes apply to this Operational Review:
 1    2022 financial year unit cost guidance: Escondida US$1.20-1.40/lb, WAIO US$17.50-18.50/t, Queensland Coal US$85-94/t (which includes BMA of US$88-
      96/t; divestment of BMC was completed on 3 May 2022), and NSWEC US$76-81/t; based on exchange rates of AUD/USD 0.78 and USD/CLP 727.
 2    BHP completed the sale of BMC on 3 May 2022. The transaction has an effective economic date of 3 May 2022 and volumes have been reported separately in
      the production and sales report.
 3    BHP completed the sale of its 33.3 per cent interest in Cerrejón on 11 January 2022. The transaction has an effective economic date of 31 December 2020 and
      volumes have been reported separately in the production and sales report.
 4    Excludes production from Cerrejón (divestment completed 11 January 2022), BMC (divestment completed 3 May 2022) and Petroleum (merger completed 1
      June 2022).
 5    The net gain on merger will be included as an exceptional item in profit after taxation from discontinued operations in the financial statements.
 6    The Framework Agreement was entered into between Samarco, Vale and BHP Brasil and the relevant Brazilian authorities in March 2016 and established the
      Renova Foundation to develop and implement environmental and socio-economic programs to remediate and provide compensation for damage caused by the
      Samarco dam failure.
 7    PLV FOB spot price of US$243.50/t as at 13 July 2022. Source: Platts.
 8    BHP signed an agreement for a nickel exploration alliance with Midland Exploration in August 2020.

The following abbreviations may have been used throughout this report: barrels (bbl); billion cubic feet (bcf); cost and freight (CFR); cost, insurance and freight (CIF);
dry metric tonne unit (dmtu); free on board (FOB); grams per tonne (g/t); kilograms per tonne (kg/t); kilometre (km); metre (m); million barrels of oil equivalent (MMboe);
million barrels of oil per day (MMbpd); million cubic feet per day (MMcf/d); million tonnes (Mt); million tonnes per annum (Mtpa); ounces (oz); pounds (lb); thousand
barrels of oil equivalent (Mboe); thousand barrels of oil equivalent per day (Mboe/d); thousand ounces (koz); thousand standard cubic feet (Mscf); thousand tonnes
(kt); thousand tonnes per annum (ktpa); thousand tonnes per day (ktpd); tonnes (t); and wet metric tonnes (wmt).

In this release, the terms ‘BHP’, the ‘Group’, ‘BHP Group’, ‘we’, ‘us’, ‘our’ and ourselves’ are used to refer to BHP Group Limited and, except where the context
otherwise requires, the respective subsidiaries as defined in note 30 ‘Subsidiaries’ in section 3.1 of BHP’s 30 June 2021 Annual Report and Form 20-F. Those terms
do not include non-operated assets. Notwithstanding that this release may include production, financial and other information from non-operated assets, non-operated
assets are not included in the BHP Group and, as a result, statements regarding our operations, assets and values apply only to our operated assets unless stated
otherwise. Our non-operated assets include Antamina and Samarco. BHP Group cautions against undue reliance on any forward-looking statement or guidance in
this release, particularly in light of the current economic climate and significant volatility, uncertainty and disruption arising in connection with COVID-19. These forward
looking statements are based on information available as at the date of this release and are not guarantees or predictions of future performance and involve known
and unknown risks, uncertainties and other factors, many of which are beyond our control and which may cause actual results to differ materially from those expressed
in the statements contained in this release.




BHP Operational Review for the year ended 30 June 2022                                                                                                                     9
Sponsor: J.P. Morgan Equities South Africa Proprietary

Further information on BHP can be found at: bhp.com


Authorised for lodgement by:
Stefanie Wilkinson
Group Company Secretary


Media Relations                                          Investor Relations

Email: media.relations@bhp.com                           Email: investor.relations@bhp.com


Australia and Asia                                       Australia and Asia

Gabrielle Notley                                         Dinesh Bishop
Tel: +61 3 9609 3830 Mobile: +61 411 071 715             Mobile: +61 407 033 909

Europe, Middle East and Africa                           Europe, Middle East and Africa

Neil Burrows                                             James Bell
Tel: +44 20 7802 7484 Mobile: +44 7786 661 683           Tel: +44 20 7802 7144 Mobile: +44 7961 636 432

Americas                                                 Americas

Renata Fernandez                                         Sabrina Goulart
Mobile: + 56 9 8229 5357                                 Mobile: +1 832 781 6698




BHP Group Limited ABN 49 004 028 077
LEI WZE1WSENV6JSZFK0JC28
Registered in Australia
Registered Office: Level 18, 171 Collins Street
Melbourne Victoria 3000 Australia
Tel +61 1300 55 4757 Fax +61 3 9609 3015




BHP Group is headquartered in Australia
Follow us on social media




BHP Operational Review for the year ended 30 June 2022                                                    10
Production summary

                                                                                Quarter ended                         Year to date
                                                  BHP        Jun       Sep          Dec          Mar       Jun      Jun         Jun
                                                 interest    2021      2021         2021         2022      2022     2022       2021
                                                            Jun-21    Sep-21       Dec-21       Mar-22    Jun-22
Copper 1
Copper
Payable metal in concentrate (kt)
  Escondida 2                                    57.5%        195.6     194.7         196.2       178.2     233.5     802.6      871.7
  Pampa Norte 3                                  100.0%        21.1      26.4          24.2        32.4      28.2     111.2       27.4
  Antamina                                        33.8%        36.1      35.8          38.4        36.1      39.6     149.9      144.0
  Total                                                       252.8     256.9         258.8       246.7     301.3   1,063.7    1,043.1

Cathode (kt)
  Escondida 2                                    57.5%         51.1      49.0          48.4        48.2      55.8     201.4      196.5
  Pampa Norte 3                                   100%         48.3      41.1          44.1        35.8      49.0     170.0      190.8
  Olympic Dam                                     100%         50.8      29.5          14.2        39.0      55.7     138.4      205.3
  Total                                                       150.2     119.6         106.7       123.0     160.5     509.8      592.6

Total copper (kt)                                             403.0     376.5         365.5       369.7     461.8   1,573.5    1,635.7

Lead
Payable metal in concentrate (t)
  Antamina                                       33.8%          381       378          277          282       181     1,118      2,532
  Total                                                         381       378          277          282       181     1,118      2,532

Zinc
Payable metal in concentrate (t)
  Antamina                                       33.8%       35,483    33,289       29,603       32,732    27,576   123,200    145,089
  Total                                                      35,483    33,289       29,603       32,732    27,576   123,200    145,089

Gold
Payable metal in concentrate (troy oz)
  Escondida 2                                    57.5%       38,893    41,962       42,937       36,303    45,770   166,972    166,968
  Pampa Norte 3                                   100%        4,728     6,967         5,776       7,929     8,198    28,870      4,728
  Olympic Dam (refined gold)                      100%       48,478    26,277       37,805       29,355    26,080   119,517    145,998
  Total                                                      92,099    75,206       86,518       73,587    80,048   315,359    317,694

Silver
Payable metal in concentrate (troy koz)
  Escondida 2                                    57.5%        1,234     1,291         1,462       1,270     1,311     5,334      5,759
  Pampa Norte 3                                  100%           214       273           215         261       262     1,011        214
  Antamina                                       33.8%        1,409     1,367         1,308       1,191     1,212     5,078      5,965
  Olympic Dam (refined silver)                   100%           185       191           258         149       145       743        810
  Total                                                       3,042     3,122         3,243       2,871     2,930    12,166     12,748

Uranium
Payable metal in concentrate (t)
  Olympic Dam                                     100%          614       531          287          781       776     2,375      3,267
  Total                                                         614       531          287          781       776     2,375      3,267

Molybdenum
Payable metal in concentrate (t)
  Pampa Norte 3                                  100%             -         -            -            -        71       71             -
  Antamina                                       33.8%          111       142          217          190       249      798           863
  Total                                                         111       142          217          190       320      869           863




BHP Operational Review for the year ended 30 June 2022                                                                                 11
Production summary

                                                                                             Quarter ended                               Year to date
                                                        BHP           Jun           Sep          Dec           Mar          Jun        Jun         Jun
                                                       interest      2021          2021          2021         2022          2022       2022       2021

Iron Ore
Iron Ore
Production (kt) 4
   Newman                                               85%           14,560        16,461       14,577        11,940       14,063      57,041     63,221
   Area C Joint Venture                                 85%           15,920        18,947       22,911        24,888       27,685      94,431     52,386
   Yandi Joint Venture                                  85%           18,405        11,834       12,261         8,418        6,409      38,922     68,596
   Jimblebar 5                                          85%           15,337        15,009       15,324        13,444       15,005      58,782     67,393
   Samarco                                              50%            1,023         1,048        1,029           994        1,000       4,071      1,938
   Total                                                              65,245        63,299       66,102        59,684       64,162     253,247    253,534

Coal
Metallurgical coal
Production (kt) 6
  BHP Mitsubishi Alliance (BMA)                         50%             9,253        6,715         6,300        7,944        8,183      29,142     31,884
  Total                                                                 9,253        6,715         6,300        7,944        8,183      29,142     31,884

Production (kt) 6
  BHP Mitsui Coal (BMC) 7 8                             80%             2,570        2,135         2,518        2,618          651       7,922      8,741
  Total                                                                 2,570        2,135         2,518        2,618          651       7,922      8,741

Energy coal
Production (kt)
  NSW Energy Coal                                      100%             4,492        4,238         2,967        2,577        3,919      13,701     14,326
  Total                                                                 4,492        4,238         2,967        2,577        3,919      13,701     14,326

Production (kt)
  Cerrejón 9                                           33.3%            1,784        2,060         2,176             -             -     4,236      4,964
  Total                                                                 1,784        2,060         2,176             -             -     4,236      4,964

Other
Nickel
Saleable production (kt)
  Nickel West                                          100%              22.4         17.8          21.5          18.7        18.8        76.8          89.0
  Total                                                                  22.4         17.8          21.5          18.7        18.8        76.8          89.0

Cobalt
Saleable production (t)
  Nickel West                                          100%               241          177           220          125          110        632           988
  Total                                                                   241          177           220          125          110        632           988

Discontinued operations
Petroleum 10 11
Production
  Crude oil, condensate and NGL (Mboe)                                12,205        12,751       12,345        11,367        7,057      43,520     46,042
  Natural gas (bcf)                                                     88.6          88.4         80.1          75.9         58.8       303.2      340.6
  Total (Mboe)                                                        26,972        27,484       25,695        24,017       16,857      94,053    102,809


  1    Metal production is reported on the basis of payable metal.
  2    Shown on a 100% basis. BHP interest in saleable production is 57.5%.
  3    Includes Cerro Colorado and Spence.
  4    Iron ore production is reported on a wet tonnes basis.
  5    Shown on a 100% basis. BHP interest in saleable production is 85%.
  6    Metallurgical coal production is reported on the basis of saleable product. Production figures may include some thermal coal.
  7    Shown on a 100% basis. BHP interest in saleable production is 80%.
  8    BHP completed the sale of its 80 per cent interest in BHP Mitsui Coal (BMC) on 3 May 2022. Production reported until 30 April 2022.
  9    BHP completed the sale of its 33.3 per cent interest in Cerrejón on 11 January 2022. Production reported until 31 December 2021.
  10   The merger of BHP’s oil and gas portfolio with Woodside was completed on 1 June 2022. Production reported until 31 May 2022.
  11   LPG and ethane are reported as natural gas liquids (NGL). Product-specific conversions are made and NGL is reported in barrels of oil
       equivalent (boe). Total boe conversions are based on 6 bcf of natural gas equals 1,000 Mboe.

  Throughout this report figures in italics indicate that this figure has been adjusted since it was previously reported.




BHP Operational Review for the year ended 30 June 2022                                                                                                     12
Production and sales report

                                                                                        Quarter ended                   Year to date
                                                                Jun          Sep       Dec        Mar      Jun       Jun          Jun
                                                               2021          2021      2021      2022      2022      2022        2021


Copper
Metals production is payable metal unless otherwise stated.

Escondida, Chile 1
  Material mined                                 (kt)         104,043        113,874   117,284   107,676   115,409   454,243     380,652
  Concentrator throughput                        (kt)          31,903         33,528    35,787    30,235    34,318   133,868     135,593
  Average copper grade - concentrator            (%)            0.77%          0.73%     0.71%     0.80%     0.88%     0.78%       0.81%
  Production ex mill                             (kt)           202.8          201.2     203.6     191.5     239.5     835.8       900.6

  Production
  Payable copper                                 (kt)            195.6        194.7     196.2      178.2    233.5       802.6       871.7
  Copper cathode (EW)                            (kt)             51.1         49.0      48.4       48.2     55.8       201.4       196.5
  - Oxide leach                                  (kt)             14.5         14.8      13.1       12.2     17.5        57.6        63.9
  - Sulphide leach                               (kt)             36.6         34.2      35.3       36.0     38.3       143.8       132.6
  Total copper                                   (kt)            246.7        243.7     244.6      226.4    289.3     1,004.0     1,068.2
  Payable gold concentrate                       (troy oz)      38,893       41,962    42,937     36,303   45,770    166,972     166,968
  Payable silver concentrate                     (troy koz)      1,234        1,291     1,462      1,270    1,311       5,334       5,759

  Sales
  Payable copper                                 (kt)            194.1        190.5     200.2      177.0    230.4      798.1       872.4
  Copper cathode (EW)                            (kt)             49.6         46.7      49.7       47.2     58.9      202.5       193.4
  Payable gold concentrate                       (troy oz)      38,893       41,962    42,937     36,303   45,770    166,972     166,968
  Payable silver concentrate                     (troy koz)      1,234        1,291     1,462      1,270    1,311      5,334       5,759

  1   Shown on a 100% basis. BHP interest in saleable production is 57.5%.

Pampa Norte, Chile
  Cerro Colorado
  Material mined                                 (kt)            5,498        5,378     4,782      3,516    3,604     17,280      31,019
  Ore stacked                                    (kt)            3,702        3,566     4,029      3,181    4,259     15,035      14,583
  Average copper grade - stacked                 (%)             0.58%        0.60%     0.62%      0.53%    0.55%      0.58%       0.60%

  Production
  Copper cathode (EW)                            (kt)             14.7         13.4      15.3       11.6     14.7       55.0           60.2

  Sales
  Copper cathode (EW)                            (kt)             15.4         12.1      16.0       10.5     16.2       54.8           59.8

  Spence
  Material mined                                 (kt)           21,262       21,154    24,025     24,040   26,749     95,968      77,202
  Ore stacked                                    (kt)            4,609        5,258     5,071      5,055    5,099     20,483      20,155
  Average copper grade - stacked                 (%)             0.72%        0.64%     0.66%      0.67%    0.66%      0.66%       0.81%
  Concentrator throughput                        (kt)            4,929        5,786     6,234      6,512    6,311     24,843       8,607
  Average copper grade - concentrator            (%)             0.63%        0.65%     0.60%      0.65%    0.66%      0.64%       0.59%

  Production
  Payable copper                                 (kt)             21.1         26.4      24.2       32.4     28.2      111.2        27.4
  Copper cathode (EW)                            (kt)             33.6         27.7      28.8       24.2     34.3      115.0       130.6
  Total copper                                   (kt)             54.7         54.1      53.0       56.6     62.5      226.2       158.0
  Payable gold concentrate                       (troy oz)       4,728        6,967     5,776      7,929    8,198     28,870       4,728
  Payable silver concentrate                     (troy koz)        214          273       215        261      262      1,011         214
  Payable molybdenum                             (t)                 -            -         -          -       71         71           -

  Sales
  Payable copper                                 (kt)             20.8          28.4      24.9      28.1     28.1      109.5        22.6
  Copper cathode (EW)                            (kt)             34.1          27.7      31.2      20.2     35.4      114.5       129.8
  Payable gold concentrate                       (troy oz)     4,728.0       6,967.0   5,776.0   7,929.0    8,198     28,870       4,728
  Payable silver concentrate                     (troy koz)      214.0         273.0     215.0     261.0      262      1,011         214
  Payable molybdenum                             (t)                 -             -         -         -       25         25           -




BHP Operational Review for the year ended 30 June 2022                                                                                    13
Production and sales report

                                                                                            Quarter ended                 Year to date
                                                                 Jun          Sep          Dec        Mar      Jun      Jun         Jun
                                                                2021         2021         2021       2022      2022     2022       2021

Copper (continued)
Metals production is payable metal unless otherwise stated.

Antamina, Peru
  Material mined (100%)                          (kt)            63,393       66,581       58,179     58,118   64,026   246,904    219,642
  Concentrator throughput (100%)                 (kt)            13,466       13,219       13,011     13,135   13,131    52,496     53,402
  Average head grades
  - Copper                                       (%)              0.93%        0.97%        1.00%      0.94%    1.02%     0.98%      0.95%
  - Zinc                                         (%)              1.24%        1.16%        1.11%      1.13%    1.05%     1.11%      1.25%

  Production
  Payable copper                                 (kt)              36.1         35.8         38.4       36.1     39.6     149.9      144.0
  Payable zinc                                   (t)             35,483       33,289       29,603     32,732   27,576   123,200    145,089
  Payable silver                                 (troy koz)       1,409        1,367        1,308      1,191    1,212     5,078      5,965
  Payable lead                                   (t)                381          378          277        282      181     1,118      2,532
  Payable molybdenum                             (t)                111          142          217        190      249       798        863

  Sales
  Payable copper                                 (kt)              37.3         32.7         41.9       32.9     40.7     148.2      143.5
  Payable zinc                                   (t)             32,044       32,635       32,513     29,920   30,847   125,915    144,063
  Payable silver                                 (troy koz)       1,540        1,103        1,405      1,078    1,230     4,816      5,920
  Payable lead                                   (t)                556          232          344        269      363     1,208      2,938
  Payable molybdenum                             (t)                268           86          170        199      205       660      1,204

Olympic Dam, Australia
  Material mined 1                               (kt)             2,143        1,935        1,998      2,424    2,477     8,834      8,704
  Ore milled                                     (kt)             2,429        2,024        1,105      2,122    2,436     7,687      9,487
  Average copper grade                           (%)              1.95%        2.03%        2.17%      2.21%    2.15%     2.14%      2.00%
  Average uranium grade                          (kg/t)            0.56         0.55         0.55       0.62     0.56      0.57        0.57

  Production
  Copper cathode (ER and EW)                     (kt)              50.8         29.5         14.2       39.0     55.7     138.4      205.3
  Payable uranium                                (t)                614          531          287        781      776     2,375      3,267
  Refined gold                                   (troy oz)       48,478       26,277       37,805     29,355   26,080   119,517    145,998
  Refined silver                                 (troy koz)         185          191          258        149      145       743        810

  Sales
  Copper cathode (ER and EW)                     (kt)              52.7         29.1         17.9       36.3     55.8     139.1      204.4
  Payable uranium                                (t)              1,179          536          541        236    1,031     2,344      3,816
  Refined gold                                   (troy oz)       47,300       24,654       38,768     30,935   24,622   118,979    143,596
  Refined silver                                 (troy koz)         245          126          290        182       87       685        874

  1   Material mined refers to underground ore mined, subsequently hoisted or trucked to surface.




BHP Operational Review for the year ended 30 June 2022                                                                                    14
Production and sales report

                                                                                       Quarter ended                    Year to date
                                                                    Jun      Sep      Dec        Mar         Jun      Jun         Jun
                                                                    2021     2021     2021      2022         2022     2022       2021

Iron Ore
Iron ore production and sales are reported on a wet tonnes basis.

Western Australia Iron Ore, Australia
 Production
 Newman                                          (kt)               14,560   16,461   14,577     11,940      14,063    57,041     63,221
 Area C Joint Venture                            (kt)               15,920   18,947   22,911     24,888      27,685    94,431     52,386
 Yandi Joint Venture                             (kt)               18,405   11,834   12,261      8,418       6,409    38,922     68,596
 Jimblebar 1                                     (kt)               15,337   15,009   15,324     13,444      15,005    58,782     67,393
 Total production                                (kt)               64,222   62,251   65,073     58,690      63,162   249,176    251,596
 Total production (100%)                         (kt)               72,848   70,587   73,852     66,674      71,660   282,773    284,102

  Sales
  Lump                                           (kt)               16,410   17,546   17,827     16,966      20,006    72,345     65,762
  Fines                                          (kt)               48,837   45,039   46,809     42,187      44,308   178,343    186,290
  Total                                          (kt)               65,247   62,585   64,636     59,153      64,314   250,688    252,052
  Total sales (100%)                             (kt)               73,712   70,815   73,222     67,110      72,796   283,943    283,871

  1   Shown on a 100% basis. BHP interest in saleable production is 85%.

Samarco, Brazil
  Production                                     (kt)                1,023    1,048    1,029           994    1,000     4,071      1,938

  Sales                                          (kt)                1,052    1,111      950           943      991     3,995      1,698




BHP Operational Review for the year ended 30 June 2022                                                                                  15
Production and sales report

                                                                                             Quarter ended                               Year to date
                                                        ...